Transcript 0:02 Welcome back to the Blockspace Podcast presented by CleanSpark. 0:05 Keel wrapped up its Q2 results last week, and Keel investors were in a bit of a tizzy because the company did not announce an AI lease at any of its Pennsylvania sites or its site in Washington Lake Moses. 0:19 Keel CEO Ben Gagnon said that signing three leases was a priority for the company in 2026, but he never gave a guarantee that they would reach that target. Nonetheless, investors wanted answers. 0:31 So for today's bonus episode, we have Ben Gagnon, the CEO of Keelon, to discuss the progress for these leases at its Panther Creek and Sharon, Pennsylvania sites, as well as Lake Moses. 0:43 We get into the details of permitting for the sites in Pennsylvania, the kinds of leases and structure that Keel will be seeking out once they do ink a tenant, and what they might look at in terms of financing for these sites, as well as a few other operational considerations. 0:59 Hope you all enjoy. Ben. Ben. Welcome to the show, sir. Appreciate you taking the time. It's nice to be here. Great. Always great to have you on, man. 1:09 We've got a lot to chew through, so we're just gonna go ahead and dive right in. Let's do it. This was brought up on the Q2 call. 1:16 Also, there have been a lot of questions from investors following the Q2 call, specifically about the three-deal target for end of year 2026. Just out in front, does that timeline still stand? 1:27 Are you still confident on it? Are we stretching it out? Do you have any updates for that? Yeah. Um, look, we remain incredibly confident here. Um, the commercial process is going so smoothly across all three sites. 1:42 Uh, we've got multiple high-quality tenants actively at three different tables. 1:49 And everything that we've seen over the last couple of months is really only reinforcing our confidence, uh, in the assets, in the commercial process, and the demand for the power. 1:58 'Cause, you know, when you have these conversations and, and you have a lot of different people who are reaching out to power, uh, it all just comes down to timelines. 2:05 And everyone's looking at, how do you get 2027 delivery? And when you are so focused on 2027 delivery, you know, frankly, you're just a lot more time sensitive than we are as the developer, right? 2:17 We're coming in here for fifteen t- to twenty years of contracted revenue. Um, and you know, whether or not it starts in March or April, like really does not matter in the grand scheme of things. 2:28 These are, you know, fifteen to twenty year agreements. If the start date is plus or minus, you know, a few days, weeks, or months, it really doesn't change things in the grand scheme of things. 2:38 But for customers, it's huge. And so each tenant we have at our table knows there are other tenants too. 2:44 And the fact that we've been able to go through this commercial process without granting exclusivity at this stage is a huge accomplishment in itself. 2:53 And I think it's a testament to the demand that we have and the power that people are willing to go through a process which is more competitive than obviously they would like because they are so eager to get the timelines that we have. 3:07 And so look, if you want '27 power, uh, you probably just don't have the luxury of dragging out negotiations over nice-to-haves. 3:15 And if you do, you're either gonna push out your own timelines or maybe you lose the megawatts entirely to someone else. And so that's what keeps real tension in the process and keeps everyone engaged. 3:26 And if you think back to what we outlined eighteen months ago, it is exactly the strategy that we said that we were gonna execute against. 3:34 We said we wanted to minimize the time between signing a lease and generating the first revenues and bringing that lease online because it's going to play into the improving macroeconomic, and it's going to play into the improving power scarcity. 3:49 It's going to play into de-risking the sites for, for Keel and our assets, and ultimately it should drive better commercial outcomes and economics. And, uh, that's exactly where we are today. 4:00 So yeah, we are incredibly confident on our commercial processes. So moving on into the Pennsylvania site specifically, I wanna kind of talk about permitting and, uh, environmental regs. 4:15 A kind of multi-part question here. I'll just kinda start with th-this first off. 4:20 I-i-if there is anything standing in the way between these leases kind of being signed and then broadcasted to the public, is it permitting and final sign-off for the sites that you have in Pennsylvania? 4:30 Can you speak to that a bit? 4:33 Yeah, let me kind of also just speak to, like, what is the general framework for walking through one of these commercial processes because they're, they're highly similar across all different tenants and across all different sites. 4:45 And the very first thing that you do is you do a quick back of the envelope check on timelines and economics, right? You're not negotiating at that point. 4:55 You're just validating for both sides that this is something worth pursuing and is a solution for the tenants, and it is attractive for the developer. 5:04 Once you're through that initial back check, the next thing that you do, and this is the vast, vast, vast majority of the time, the work, the conversations, it's construction and engineering and technical teams working with construction engineering and technical teams, right? 5:20 So our teams work with the potential tenant teams. They work alongside the architecture and engineering firms, the general contractors, the equipment manufacturers. Everyone has to be working together in those timelines. 5:34 And so, you know, I don't know what the exact number is, but I'd say somewhere probably between like seventy-five, eighty-five, you know, percent of the conversation is around engineering. It's around timelines. 5:47 It's technical work. It's not negotiating of the terms. And so really the, you know, the permits remain one of the last few items that investors can noticeably, uh, see just by what's out there in the public realm. 6:02 But it's not as if the permits are a light switch that, you know, you flip one, you get one, and then a lease is signed immediately. It's one of the last things that are remaining there for the investors to see publicly. 6:13 But in the background, we're focusing on, on continuing with the, uh, finalizing, double-checking, triple-checking the engineering, the, uh, commercial side, the general contracting side, the equipment manufacturing side, so it all lines up. 6:29 Um, and that's, that's really all that's left in order for us to be comfortable with, with signing a lease. So, um, there's still a few more things. Like I said, it's not a light switch. 6:40 But, um, everyone is, is very, very motivated to secure the power, and that is exactly what we're motivated to do as well, is to secure the tenants. 6:51 So o-on that note, zooming in here, y- there are a number of [clicks tongue] uh, there are a number of permitting and environmental sign-offs that y'all need. 7:00 You mentioned that the Panther Creek's final environmental permit on the call is, quote, "taking a few months longer than anticipated." Why is that? 7:09 And as a follow-up, can you give us a kind of TLDR breakdown of exactly what permitting and regulatory sign-offs y'all need for Sharon Panther Creek? Yeah. 7:21 So the, um, like I said, you know, I think with you guys before, right, there's three general buckets of permitting. You've got zoning, you have development, and you have engineer- or environmental. 7:32 You know, zoning tends to be your controversial one. It's the one where you have town halls, and the community engagement is very, very high. 7:39 It's also the one where, you know, the necessary fact sets of the patter- of the project might not necessarily be what determines the outcome because it can be political, it can be emotional. 7:49 Um, once you're past zoning, which is the controversial one, then you go through development. Development tends to be very engineering and process driven. 7:57 It's hey, you know, the setbacks require you to be twenty feet back from the property line. There are building restrictions no higher than, you know, X feet. You need to meet these kind of noise requirements. 8:07 You need to have these kind of light requirements at different times in the day. It's not very political, right? 8:14 It's very much a, these are what we agreed to as kind of the frameworks and the parameters to guide construction, and are the plans that you're submitting compliant with those? If you are, great. Proceed. 8:26 If not, these are where you're not compliant. This is what you need to revise to be, you know, um, compliant, and then you can proceed. And then the same thing with the environmental. 8:37 Um, the environmental is very process driven. It's very data-driven. It doesn't tend to be political. 8:42 The permits that we have remaining in Pennsylvania largely have to do with stormwater waste runoff and connecting into municipal sewer systems. These are not politically controversial permits, right? 8:54 We're not talking about flushing millions of gallons of water a day into a municipal sewer system. 8:59 We're talking about making sure the employees on site have the normal facilities that any facility would have, and they're connected into the municipal sewer system. 9:08 Um, we're talking about making sure that the standard plans for any kind of development, um, are there for stormwater waste runoff and how that's gonna be controlled and managed with the, with the layout of the land. 9:19 So these are pretty standard. They're pretty straightforward, and there's nothing to be read into on the delays. There's just two different departments in Pennsylvania for the Department of Environmental Protection. 9:31 There's an eastern office, which serves obviously the eastern side of the state where Philadelphia and the vast majority of the population and the industry is. 9:39 And then there's a western office which, you know, serves a much smaller population and a much smaller industrial base, which is where Sharon and Scribd Grass are. 9:48 And so at Sha- uh, the western side of the state, fewer applications, fewer permits to work through, and they have less of a backlog. 9:55 On the eastern side of the state, way more permits to work through, a bit less, a bit more understaffed, and they have a bit more of a backlog. 10:02 But we haven't received anything in the permitting process that would give us, you know, pause, concern, alarm, and nothing for the tenants as well. 10:10 Um, these just continue to remain moving forward at the same time that we're running the commercial process, and we have not had one concern from the tenants around the remaining permits at either of those sites. 10:24 So I'll throw a question in here. Um, looking at Moses Lake in Washington, uh, I think it's your smallest site, eighteen megawatts, and it looks like you, uh, did not exercise the option to expand it- Yes... 10:39 another ten megawatts, which would, would have been twenty-eight. What's the reasoning for that? I'm, I'm kinda curious. Everyone wants more power. Why are we not doing more power? 10:49 Uh, so it's a great question, and let me walk through kind of the reason why we got the option in the first place and why we walked away from it. 10:56 So, you know, obviously Moses Lake at eighteen megawatts is the smallest site that we have under active development. 11:02 Um, and it just because of the scale limits itself down to, you know, a different kind of, of potential customer. 11:10 What we, you know, thought would be a very attractive, you know, um, kind of, you know, sweetener to any sort of a, um, a tenant contract in Moses Lake would not only be to have eighteen megawatts, but would be to have the ability to expand beyond that and continuing growing. 11:26 Because at every site that we've seen with every tenant that we've spoken to, they don't just want first power, but they want a relationship to grow over time with and to scale over, over a longer period of time. 11:38 And so we thought it would be an attractive thing for us to do, acquire a low cost option, have that optionality in the commercial process. 11:46 If tenants would be interested in the site but maybe they need a little bit more power, we would have that there to provide greater optionality and greater value to the tenant. 11:55 Um, so- But what it's come down to is, is that like I said earlier, it's all just about timelines. And the 10 megawatt option was not for a 10 megawatts adjacent to our site. 12:06 It was a 10 megawatts at a different site in the same town. Um, it was going to be associated with much longer timelines. 12:13 And one of the things is, is with smaller sites is a lot of the costs just don't amortize as well over way fewer megawatts. 12:20 Some of the things are fixed regardless of if it's 18 megawatts, 100 megawatts or 350 megawatts, it's the same amount of work. 12:29 And so, you know, what we would rather do is we, you know, we brought that to have optionality for the tenants and provide extra value for the tenants. 12:36 But we would rather focus on the better opportunities that we have in our portfolio to acquire and secure larger sites, which don't have the same kind of economy of scale disadvantages of something like a 10 megawatts. 12:50 We'd rather focus on bigger sites, um, especially in the East Coast, Northeast and the Midwest area where we think inference is going to be, uh, the highest, you know, demand market. 13:02 And that's where we want to try and, and focus our efforts moving forward. So, um, we think it's, you know, the right thing to do to continue to grow the pipeline and allocate resources internally, uh, effectively. 13:15 Uh, going back to Pennsylvania, you talked a bit about permitting, um, and I want to ask a question about the Sharon site, which if it looks like you've collapsed the 30 and 80 megawatt phases into one 13:30 single 110 megawatt phase, um, what's behind that decision? Uh, yeah. Yeah. So, uh, that's what we're working towards right now. 13:41 We're, we're pretty close to thinking that we're, we're gonna have that finalized and done, but it's not a, a done deal today. 13:46 Um, the reason why is because even the proximity between the racks themselves have huge latency impacts. 13:54 And so, you know, the closer that we can get the compute to itself, the better it is for the performance of the site and for the tenant. 14:03 And so what we wanted to do was we wanted to try and consolidate the power density as much as possible. The original design was a little bit more, uh, spread out across, you know, multiple buildings. 14:14 Here we're trying to consolidate it in closer and closer so that it is, you know, an ultimately better product for the end tenants. 14:21 Um, we think that we've accomplished that with, uh, our engineering or we're about to accomplish that with, with our final engineering plans. 14:28 Um, and we look forward to talking about that publicly once it's final, you know, with the new updated plans, the site images and the renders and everything else. 14:37 Uh, but ultimately it was just trying to make a better product for the customers. So it's kind of like the Jensen scale up, now you're trying to scale out- Correct... idea. Gotcha. So Ben, 14:49 with regards to leases in, uh, you know, potential leases in the pipeline, you, you've said before that companies like Keel are kind of in this Goldilocks zone, and I kind of read that as you're not a first mover, but you've gotten to see how certain deals have been moved across the finish line, and we're actually seeing dollar per megawatt deals for powered shells move upwards. 15:12 I mean, the, the, the infamous example of this is Core Scientific with the CoreWeave deal. Great deal at the time, CoreWeave, you know, paying for the build-out. 15:20 But if you actually look at the unit economics, there have been better b- deals struck since, and you can say the same about some of the earlier deals with Terawulf and Cipher as well. 15:27 We're starting to see, uh, you know, this segment kind of feel out what makes the most sense, and it seems like they're able to juice more from these deals as the timeline goes on and we continue to move into this CapEx cycle. 15:42 Long-winded way of asking this, and I know you can't give too many specifics, but with regards to a structured deal, what kind of economics and deal structure for these leases is Keel privileging? 15:55 Like, what would you like to see in terms of terms, duration, et cetera? If you could just, like, give us a teaser. 16:02 I know you can't speak to specific numbers, but just curious where y'all's head's at in terms of how you structure these things. Yeah. You're-- It's-- I mean, it's a great question. 16:09 You're right, I can't speak to specific numbers. But, you know, we, we talked about this 18 months ago, the economics were gonna continue to improve. They have, right? 16:18 Um, and it's not a perfectly straight line, but if you chart out every single lease that has been announced, you know, and you put it on kind of an apples to apples footing, like a per megawatt basis or per megawatt per month basis, wherever you wanna look at it, like, you'll see that the direction is pretty abundantly clear, right? 16:34 Like, the economics have continued to improve up and to the right, uh, for the last 18 months. And so we do think that there is a, a second mover advantage. 16:43 Um, you know, we also can avoid a lot of the mistakes that, you know, people have learned the hard way, right? 16:49 Um, you know, we saw earlier on what, what happened with people giving exclusivity too early on in the commercial process, and ultimately it resulted in massive, massive delays because you grant someone six months exclusivity and you shut yourself off from everyone else, then you have to grant the next person six month exclusivity starting from zero, and then the next one. 17:11 And so, you know, we've learned that, um, from our peers, you know, the good and the bad of what's happened. 17:17 We've seen the market evolve, and we've been able to, you know, kind of play into what we've seen as the trend for economics and continued power scarcity to our advantage. 17:27 So, um, you know, th-that-- with that overall framework in mind, um, what I can speak to in terms of deal structuring is, you know, we prefer triple nets. We're not trying to, you know, uh, be 17:41 crazy in creating creative new structures. You know, we're not looking to sell, you know, rum raisin or pistachio cream. Like, we like vanilla. Vanilla is totally good. Um, vanilla sells all over the world. 17:55 It's popular everywhere. Everyone likes it. It's easy to understand. You don't need to get too exotic. 18:00 Sometimes simple is better, and I think for the investors, they prefer something that's easy to model, easy to understand, easy to forecast, minimal variables. So that means triple net. 18:12 We like triple net structures across the board. Um, and we should expect to be getting, I think, triple net structures across the board, with one exception being Moses Lake. 18:21 And that's just because the customer profile there is so different than at Sharon or at Panther Creek, and they really need a more turnkey solution, where the larger players are looking to take a lot more, um, you know, operational involvement and control. 18:36 And so, you know, we're able to, uh, proceed on triple net, which is the preferred option for ninety-nine percent of our portfolio. 18:43 For the one percent of our portfolio that's Moses Lake, we'll take the structure which is best for the, you know, maximizing value for that particular site. Um, but overall, we are very focused on triple nets. 18:55 I'm, I'm gonna start demanding more food analogies from other executives. Also, my wife in shambles. She thinks that vanilla is a boring flavor. I think vanilla- She's wrong. 19:04 I actually like vanilla more than most rules... vanilla rules. Yeah. CleanSpark is a market-leading data center developer with a proven track record of success, Nasdaq CLSK. Vanilla freaking rules. 19:14 Everyone likes vanilla except for your wife, I guess. [laughs] So it's generally a, a, a pretty good way to go, I think. 19:21 So Ben, I have one more question for y'all specifically, and then I wanna zoom out to the sector at writ large. 19:27 Curious about lead times for equipment and whether or not Keel has moved forward for securing long lead time items, whether or not you're seeing any snags within the supply chain, considering there's so much demand. 19:41 You could just speak to that, uh, the supply chain logistics side of things very quickly. Yeah, I can. 19:46 And, you know, slightly different, um, at each site, but j-- by and large, what we've done is, uh, Moses Lake, absolutely everything is secured. It's contracted. 19:55 It's either received on site or it's being manufactured somewhere else, and we're waiting to receive it on site in the coming months. 20:02 Um, with regards to Sharon and Panther Creek, what we've been doing, this is what I spoke to earlier in the commercial process, you run all of that simultaneously. 20:11 Like, you have to run two parallel paths because different customers could have different equipment choices, and they could wildly differ. 20:20 Um, there are big changes, especially when it comes to things like backup generation solutions. 20:23 That's usually one of the big areas where people have very differing opinions and equipment choices, and that can represent, you know, two to three million dollars a megawatt in terms of CapEx. 20:34 So that's a big one that you don't want to put on your balance sheet unnecessarily. 20:38 And so what we do is we go parallel paths with the tenants, with the general contractors, the AE firms, and most importantly, those equipment manufacturers to make sure those supply chains and the, the timelines are all lined up. 20:52 And then you ideally execute all at the same time. 20:55 What you don't wanna have is you don't wanna have, you know, uh, an unmatched liability where we've just signed up to procure, you know, three billion dollars of equipment that we, you know, don't have the tenant for. 21:08 And we also don't want to sign up for a tenant to deliver three billion dollars of equipment that we don't have secured. 21:14 And so the way that you try and balance this is by concurrently running those processes in parallel and then getting to the point where you can sign all the agreements all at the same time and not have those unmatched liabilities. 21:27 And at the stage where we are right now, working through with our Go Vertical partners and the equipment supply chain, we're hitting those earliest RFS dates in twenty twenty-seven, um, with a little bit of ramp into twenty twenty-eight for Sharon and then a ramp through twenty twenty-eight for Panther Creek. 21:43 So the timelines that our customers want, first power online in twenty-seven and continuing to ramp from there, uh, we're very confident we can achieve those timelines, um, based on all of the work that we've done to date, all of the contract negotiations we've done, and all of the work with the supply chain manufacturers. 21:59 But that's, that's generally the framework how you want to, uh, to run that. I appreciate that. All right, last question from me. I'll toss it to Charlie for a closer. I know we gotta get you out of here soon. 22:09 So you said on the call that you're, quote, uh, you're watching, quote, "The increasing amounts of intercompany financing across the industry," end quote, as a top risk. 22:20 What specifically concerns you, and how does this affect Keel's approach to tenant credit support, and also what financing options y'all would entertain once you have a lease on the books? Yeah. 22:32 So I think that came up in, um, analyst Q&A in response to a question of, like, what is your biggest risk factor for, for Keel rolling forward? And, um, you know, the answer that we gave was, we think it's macro, right? 22:46 The stuff that the company is, is executing against, we are incredibly confident in. We know that the demand is there for the power. We know that we are making the progress that we want on the permits. 22:58 So we are very confident in what we are in control of. I think the, the one thing that, you know, is constantly changing in this space is the macro environment, right? Um, and it's changing on a, on a daily basis. 23:12 Monday is something new. Tuesday is completely different. Wednesday is somehow different than that. And by the time you get to Friday, it feels like a month has passed, and it's been five days. 23:21 So, you know, those are the things that we really, you know, try to, try to keep a closer eye on, um, is just what is going on in the broader financing market. This is a very capitally intensive industry. 23:33 The cost of financing these projects can really change the ultimate economics of the project themselves, and we wanna make sure that we're hitting the market at the times that we wanna hit the market, where we can get the best economics and the best deals. 23:49 And sometimes, you know, high-yield market will just shut down. Sometimes it's really, really cheap to do a convertible. Sometimes there's a tremendous amount of low-cost debt, sometimes there's not. 24:02 And so what we are keeping an eye on, you know, is this macro factor of what's going on in the world. How is this impacting the broader industry? 24:10 What does that have in terms of implications for, uh, supply and demand side of the equation? And, you know- We are really focusing on how do we get the most value out of what we have in our pipeline. 24:23 And so understanding that macro piece, understanding the timing component of these things, we think is really mission critical. So to wrap up, kind of a broad industry question about AI models. 24:37 Um, open models have been having a bit of renaissance. Jensen had that big letter, NVIDIA, and pretty much everybody signed it except for a conspicuous couple companies. Um, 24:48 in a world where open weight models, uh, become much more prevalent, maybe even dominant, what happens to the market? Who wins in this scenario? Who loses in this scenario? Yeah, what does this look like in your view? 25:04 Um, you know, anyone's guess at this point is, is really as, as good as mine. 25:08 Um, but I think what we're seeing is we're seeing there is starting to be a lot of, uh, segmentation in the market, and people are starting to become more and more niche players, right? 25:20 You're seeing platforms come out, um, like Higgsfield, which is trying to establish itself as like the premier like image video generation platform, you know. 25:31 And then you've got that as completely separate from Claude for Enterprise, which is completely separate from ChatGPT, which is more consumer friendly or consumer directed. 25:40 And then you've got, you know, the open weight models out of China. How all of this is gonna evolve, I don't think anyone really knows. 25:47 But I think what it shows is that there's gonna be more than one model dominating across the market, because as with everything in this world, uh, people like to specialize, people like to focus in, and people generally don't want to have, you know, like, um, one solution for absolutely everything in the box because you can't be the best solution for everything in the box when you're a solution for absolutely everything, right? 26:17 If you are a company, you don't have, you know, one system, right? 26:22 You may have payroll, you may have a legal system, you may have a business development system, you have a customer relationship management system, you've got finance systems, you've got payroll systems, right? 26:32 It's not, I think, reasonable to think that one system is going to rule all of those systems. I think we're gonna see increasing fragmentation, specialization of these models start to emerge. 26:43 Um, and I think it's a great example of Jevons paradox playing out here, because the reality is, is that, you know, there's always different ways that you can do price segmentation, and you can try and capture more value for premium services or lower value for lower quality services, right? 27:00 This is the-- You know, this is a very proven economic model. You know, airplanes sell, uh, economy, premium economy, business, first class. Trains do a similar thing. Cruise ships do this. 27:13 You know, the China model has been, um, focusing on low cost volume, you know, in terms of just how they produce goods and services, and the Chinese or the US system has always been focused on higher quality, higher value. 27:26 So in some situations, maybe you're like an, you know, a defense industry contractor. You probably maybe don't want the open weight model. 27:33 Maybe you want the highly specialized model for, for you, which is going to be maybe it's Claude or maybe it's something you've developed specifically for yourself. 27:43 Um, but I think the more applications that you see, the more models that you see, the more optionality that there is, people will start to do 27:51 price segmentation, um, more and more, and I think, you know, you're gonna see enterprises focus more and more on the higher quality models, and you're gonna see retail gravitate towards the cheaper Chinese models. 28:06 Because if, you know, for us as a business, um, I don't want slop, right? 28:11 [chuckles] Like we, we use Claude in our management team, and, you know, we, uh, encourage everyone to be asking Claude questions and trying to, to, to play around with Claude as much as possible. 28:23 We don't want anyone running anything through, you know, uh, open weight models right now. 28:28 Like, we want everything on an enterprise system that is, you know, secured, that is safe, that is, you know, signed off by our IT team, is reliable. 28:37 Um, but you know, if I go home and I wanna generate a, you know, cute picture of a dog or something, you know, I'm not gonna be using Claude, right? I'm gonna be using a different model. 28:47 I think it's just showing how early we are and the, the future is gonna be increasing fragmentation, um, and specialization. Ben Gangyan, CEO of Keel, Captain Keel himself. Thank you for joining, man. 28:59 Really appreciate it. Best of luck with the rest of the year, and we'll have to run it back Q3 when y'all have results then as well. Thanks guys. Looking forward to it. Thanks for your time, Ben. Thanks, Ben.