Transcript 0:00 Rumors are swirling that Iren has to re-network its Childress AI site for Mic- Microsoft after the tech giant requested a redesign across all of its data halls. 0:12 But rumor also has it that that won't necessarily materially change the delivery timeline for this site, even if it bumps back the second phase rollout by just over a month. 0:23 You're listening to Blockspace Live, and for our top story, we'll be diving into a little bit of scuttlebutt, Charlie, on Iren's flagship data center and exactly what we should expect over the rest of the quarter for delivery of all four data halls for Childress. 0:38 Following that, we have an interview with independent journalist Aaron Ren, formerly of the Manhattan Institute, to discuss why the data center industry, industry has overplayed its hand during the AI CapEx boom and why, as he puts it, they kinda have themselves to blame for all the backlash. 0:55 To cap the show, Needham and Company analyst John Todaro will join us to talk about their spooky season note about the AI stock scare ahead of Halloween and whether or not he thinks this is a material breaking of the AI business model for data centers, or if it's just a bump in the road. 1:16 You are listening to Blockspace Live, co-hosted by Charlie Spears and Colin Harper of Blockspace Media. We do this live show every weekday at 1:00 p.m. 1:26 Eastern, featuring quick stories, executive interviews, and analyst commentary on the American data center build-out, as well as markets, technology, and things in that wheelhouse. 1:40 If you don't get enough on the live stream and you want more Blockspace content, we have a website, blockspace.media, with more written stories, a lot of which we cover here live on air. 1:53 We would normally kick a stream off with a tweet of the day, but we have a heavy front-loaded story on Iren that we're gonna give to you right after a word from our sponsor, Soluna. 2:07 [upbeat music] Soluna Holdings, Nasdaq listed ticker SLNH, develops data centers co-located with wind and solar plants, turning surplus renewable energy into computing power for AI and other intensive applications. 2:27 We are proud to partner with Soluna Holdings here at Blockspace. If you would like to learn more, please visit solunacomputing.com. That is solunacomputing.com. 2:43 Iren is likely on track to deliver its flagship AI data center for Microsoft, despite rumors of delays that could push back the deliveries of the second data hall by roughly one month. 2:55 Iren delivered Horizon One, the first 50 megawatt building of the 200 megawatt Childress Data Center, in August, and rent has commenced at the site. 3:03 In the most recent earnings call from Iren, the company disclosed that Horizons Two to Four would be delivered sometime within this quarter, and that the contract includes grace periods for Horizons Two to Four extending from mid Q4 2026 to the beginning of Q2 2027. 3:22 That clause could come in handy because unconfirmed rumors hold that Horizon Two could be delayed by roughly forty-five days. 3:31 According to Iren investor Jim Liu, Iren held a call with a group of large shareholders yesterday in which they sought to quash rumors about substantial delays at Childress, which were the result of a rumored Microsoft redesign of the networking at the site. 3:46 Liu claims that Horizon Two is facing up to a forty-five day delay, Horizon Three is facing minimum delays, and that Horizon Four is now targeted for delivery in late December. 3:58 All right, Charlie, I've got some more details to comb through, but I want to address the elephant in the room here obviously. 4:02 We have no confirmation from Iren or Microsoft about these delays, but rumors have been swirling about them for the past week or so. We've seen redesigns impact other sites, so it's plausible. What's your take? 4:15 Uh, again, it's a rumor, but I'm inclined to believe it because it's very specific. 4:20 It's a very specific and fixable problem, and it's also a pretty boring problem because this would only delay it, it looks like, within, uh, the kind of acceptable grace period they have in the contract. 4:33 I think what we have to figure out now is, which is what affec- affects the overall financing and money side of the project, which is whose fault was it? Back to you. Yeah, and Liu has a bunch of comments regarding that. 4:47 But first, just to kinda dig further into the cause of this delay here, digging into the report further, Liu claims that Microsoft requested a change to Childress' network topology across every data center hall. 5:02 Horizon One also requires recabling, according to Liu's report, but he claims that the redesign won't impact billing at the hall, even though it could take four months. 5:10 Quoting directly from his tweet here, "The recabling on H2 was given a timeline of forty-five days, while H1 will be recabled while running workloads, and that process was given a timeline of four months. 5:22 [lip smacks] H3 will be delivered, uh, Horizon 3 will be delivered with Horizon 4 as a super cluster, and Horizon 4 hasn't begun recabling, hasn't begun cabling and will maintain the December timeline. 5:34 Horizon 1 recabling will take much longer than Horizon 2 because Horizon 1 is already accepted, so the changes will be made during maintenance windows and stages. Horizon 1 will be running live workloads and billing." 5:47 Liu claims that, that the request from Microsoft came one month after its test following the site's delivery. 5:56 Once Microsoft started using the data hall fully, it discovered issues for networking bandwidth between each GPU rack and the full cluster at Horizon One. As for who is to blame- 6:08 Liu places that at the feet of Microsoft's platform team, specifically saying, quote, "Microsoft's bare metal team signed off because Iron met NVIDIA DSX specs. 6:20 However, the Microsoft platform team, when deploying software, needs a specific topology for their workloads and did not communicate with the bare metal team. 6:29 This explanation is based on the fact that the issue was found more than one month after acceptance and usage began. 6:35 During this one month, it's likely that only then did Microsoft's AI research team start running workloads. 6:40 Most likely, Microsoft's platform team did not gather requirements from Microsoft's research team and did not relay full requirements to Microsoft's bare metal team." Whoa. Can I inject here? Like so- Yeah... 6:51 two Microsoft teams weren't talking to each other, it sounds like the rumors are, and that's why they didn't have the bandwidth for this particular... the topology of this load? Yeah. I would say grain of salt here. 7:05 This is a mega Iron bull- Yeah... right? And if the reports about this shareholder call with the Iron team, if, if the reports are true, you're getting Iron's side of the story, obviously. Yeah. 7:18 So as my grandmother used to say, there are three sides to every story. We're just getting Iron's. Microsoft has its side, and then there's obviously some truth somewhere in the middle. 7:28 Uh, but Liu, Liu does say you have to take into account that Microsoft is a massive company. It's one of the largest tech companies in the world, so 7:36 it's easy to see how something like this could get lost between all of the workflows. That being said, Charlie, I think that your gut is a little bit right here in saying that is either a total, uh... 7:47 That, that's a complete fumble for Microsoft, or there's something that doesn't totally add up here. 7:53 But one last thing I want to point out before we close on this specific part of the segment, I don't have the full breakdown here from Franz 'cause it's behind a subscriber paywall, but he digs in. 8:05 This is Franz Backer, another, I, I should say, very voluble Iron investor who tries to get into the details about whether or not these sites are ready to come online. 8:16 So he has some satellite imagery, and I got some of the commentary from Grok from his X post here, where he says that Horizons 2 through 4 are proceeding according to schedule. 8:28 Quote from the post, "Iron's chil- uh, children's... Uh," oh, excuse me. Um, "An I- Iron Children update, uh, on 10/14/2026. Not so recent because of rain, but four days further, a few things can be spotted. 8:44 Horizon 4 seems to have installed three generator buildings. I can't see addit- additional MER buildings. Horizon 2 looks no longer under construction. I think that they are busy inside with the cabling and compute. 8:55 Horizon 3 is hard to judge from this picture. I hope the high-definition satellite image we have ordered will arrive soon." And... Go ahead. I will, I will inject here. 9:05 Horizon is, you know, only a three hours drive from me here in Oklahoma, and it has been very, very rainy for the past few weeks. So I can do some primary reporting and confirm it's probably a little bit of rain, too. 9:18 Well, and before I ask you, Charlie, about that's good context, and before I, uh, I ask you about whether or not the rest of this is just copium from the Iron investors- Yeah... 9:26 my question, uh, or m- just a quick breakdown of what's at stake here. This contract with Microsoft is 9.7 billion in contract value over roughly five years for 200 megawatts at this Children's site. 9:38 And again, they're trying to get every single building online by the end of the year, and if not, then they have a clause within their contract that it will give them a grace period into Q2 2027. 9:49 So Charlie, final thoughts here. 9:50 Copium from the Iron crowd, uh, true to word, or is it too early to obviously tell until we get confirmation from Iron management, which could come in its, uh, earnings call for the, uh, Q1 2028 fiscal year? 10:04 Look, it's probably a little bit of copium. Uh, I don't see this as, like, a huge deal unless the cost overruns are, like, massive and significant. Again, I... 10:13 It look, it looks like it's within the contract, like, grace period, like, con- uh, conditional window, so maybe it's just delayed a little bit. 10:22 Um, this is what, you know, the customer's always right, and sometimes when the customer's wrong, you delay the project to relay the networking between your NVL 72 racks so that they can talk to each other better. Um, 10:36 I don't see this as, like, a big deal 'cause this just means maybe... This is, like, the first major deal I think that Iron has with Microsoft as they roll these, uh, these racks out. 10:47 Um, not surprised that there's some delays. I mean, it could... Think about the other kind of delays it could be. It could be, uh, local jurisdiction, uh, putting the kibosh on it. 10:58 It could be, like, a structural, like, a hardware, uh, infrastructure sourcing problem. It could be a labor issue. Those would be much worse in my opinion than having to pull out, I think, some just cabling between, 11:11 uh, between some, uh, high performance racks. 11:15 Yeah, and this obviously doesn't substantiate what Iron has or hasn't said about this, but just for some context as to whether or not you can expect delays at a site like this, we can look no further than Cipher to confirm that changes in designs and specs can delay a data center. 11:30 So obviously, Cipher extended its Barber Lake facility with a 10-year added to its original contract. 11:38 With that, though, came a redesign for some of the data center halls, and Cipher in its SEC filing for the material change according to the press release said that the tenant requested design modifications by Fluid Stack to Barber Lake alongside revision to construction schedule, um, will move the data halls 3 and 4 from Q4 2026 completion to Q1 2027. 12:02 And with regards to Microsoft itself, we also have this report going back last year to January- For its Arizona campus with OpenAI. A quick rundown on this. 12:13 Microsoft originally planned to install GB200 racks containing at least 50,000 Blackwells. OpenAI requested earlier deployment using Hoppers H200s instead of waiting for all the Blackwells. 12:25 Microsoft shifted the facility to H200 systems and reduced its planning for Blackwell to roughly one quarter of what it originally had specced out. 12:34 When the Blackwells did arrive, the systems were encountering overheating and connectivity problems and contributed to hardware availability delays. 12:40 So that's a different problem in the sense that the overheating is a much different problem in terms of thermal management for the racks themselves, but it kind of falls in the same category of 12:52 there are unforeseen snags sometimes when you're building these things. Also, a redesign and respec-ing for things like networking or the rack designs themselves is happening more often than not. 13:02 It just doesn't make the news. A, a company's obviously not gonna talk about that because investors might not know how to price in that risk, right? 13:09 Yeah, and if you consider that these are the first time these, these, these, uh, Vera Rubin racks are being deployed, like at scale, I mean, not at this site specifically, but we're in the first, like, inaugural deployment of these. 13:22 Not surprised. Uh, new hardware all around. Whenever I build a computer, I'm a PC gaming nerd, uh, I mess up. I gotta take my GPU out and reset the CPU. 13:33 But they are doing that on the billion dollar end, uh, large scale industrials, you know, size. So not surprised. I think it's, uh, it is a question of who's gonna have to pick up the extra cost. 13:43 So we'll see what that looks like. We have in the wings, we have Aaron Renn, American culture writer. We're gonna talk about how the data center industry fumbled the public narrative after a word from our sponsor, Luxur. 13:59 [whooshing sound] This episode of Blockspace Live is brought to you by Luxur's Commander, Bitcoin miner management software for enterprise operations. 14:12 Luxur's Commander gives you real-time fleet monitoring, bulk remote commands across your fleet, and Intelligent Miner. 14:17 That's an automated profitability engine that runs every five minutes and adjusts your fleet's power settings to live energy and hash rate markets. 14:24 In fact, our cop back tests show 10% improved profitability with intelligent mining versus binary mining. 14:30 Commander Pro is roughly half the cost of competition, about $100 per megawatt or a 25 basis point pool fee adder, but you can also try it free for 60 days. 14:39 So if you'd like to learn more, go to luxur.tech/commander to get started. All right. Say goodbye to Colin. We're gonna bring on up Aaron. Aaron Renn, welcome to Blockspace. Thanks for having me on. 14:55 Yeah, thanks for coming on. I sent you a cold DM, and you replied. Huge fan of the Substack. 15:00 Um, you are a, an American culture writer writing about human, cultural, and institution- institutional foundations, American flourishing during an era of transition centered around the Substack. 15:13 And you dropped a piece a couple weeks ago, which caught our eye, because we're a data center show that talks, that, that sometimes ventures into culture. You're a culture writer who ventured into the data center world. 15:30 This is where we're gonna have our conversation. Why, Aaron, did the data center story pop up on your radar and you decide to write about it originally? 15:41 Well, before I branched out into culture, uh, I was focused on urban policy and sort of urban affairs. Uh, I was with a think tank in New York working on that. 15:52 And I still write on those issues, so things around economic development in cities, uh, and, and rural areas was some of what I kept an eye on. And of course, 16:03 the data center thing is both a major cultural phenomenon, but also gets into the economic development side, uh, of it. So it was a natural interest for me. 16:12 And then my background from my old Accenture days was in technology consulting, so I, I do know how to code, and I, I actually worked in a data center, actually, when, back in the '90s. Oh. 16:22 I don't want to claim the same [laughs]... Not like today's data centers, completely different. It probably looked a lot different. It was a lot different. But, uh, yeah, it was in a data center, yes. 16:32 So, um, one of the things which we've talked about, and I, you really identify at the top of the piece, is that this is not a left or right. This is not necessarily even a, a wealthy or, or not wealthy problem. 16:46 This is a pretty cross-cultural pushback, which is unique. One of the first we've seen in a while. Describe this, this, uh, this pushback for me. Describe, like, the anti-data center movement we're seeing. 17:00 There are two things that to me really stick out as modern cultural phenomenon that cut across party lines and cultural lines. One is data centers. The other is flock cameras. 17:12 Uh, if you've been following that, these license plate reading cameras. And both of them come out of kind of a low tr- what I would call a low trust environment that we have today. 17:23 People are very distrustful of sort of politicians, of institutions. That's well documented. There's also the situation where people are very anxious about technology, and particularly AI and its impact on their lives. 17:40 Uh, so people have a lot of anxiety. And I do believe data centers got caught up in the general anxieties over artificial intelligence. But then also, uh, th- there was an internet phenomenon. 17:53 I think social media and the virality through a lot of the influencers put these things into the public mind, and then it just rips through the culture in a very short period of time. 18:05 Uh, I didn't trace the exact origins of this on the data center side with, with the flock cameras. 18:12 A lot of it traces back to the campaign of this sort of insurgent right candidate in Florida for governor- Fishback was his name. 18:19 He got, like, 10% of the vote in the primary, but flock cameras were his issue, and then it caught fire with the Washington Post and other articles, and then went crazy. And so that, that's one. 18:31 And then I do think these things started popping up in a lot of states and a lot of places, and some of the newer kinds of data centers, uh, are large scale. 18:41 Not all of them, but some of them are truly gigantic complexes on thousands of acres. 18:46 [lip smack] And the traditional economic development playbook, which, uh, involves a lot of non-disclosure agreements and kinda negotiating everything behind the scenes, sorta didn't, you know, intersected with, again, all these other things around low trust and just gi- garden variety nimbyism. 19:04 People don't like anything these days. Uh, and I think all these factors intersect at, and a data center just sits right in the middle of all of them. 19:13 Uh, you got straight to one of my, uh, one of the questions I wanna ask because, um, I live in a red state, and you describe red state/blue state tactics and the different ways these, um... 19:27 You're critical of, like, how the data center industry has been operating. Well, you talk about the NDA issue, and I'm seeing that in my home turf here in Northeast Oklahoma. 19:36 The- One of the reddest states in the union, and, uh, the people hate it. Um, they hate the, the obscured, like, deal-making that is happening. Um, describe how that works for me. 19:49 Y- you kinda talk about it in the piece, but I'd love for you to go into exactly, like, how it's looked in the past and why this particular incenses the public these days. Sure. 20:00 So today, when a, some corporation is trying to decide where to put a facility of any type, they often hire a specialist called a corporate, excuse me, site selection consultant, and these people basically specialize in helping you pick the place. 20:18 And they do some genuine research around things like tax rates and, uh, labor force availability and infrastructure and all of that. 20:27 So there's a legitimate function to it, but part of their job is also to play states and s- and towns off against each other to maximize the subsidies there. 20:38 So this is the game that's played, and the biggest one, which didn't involve really NDAs, but was a huge thing several years ago, was Amazon's HQ2. 20:48 The whole country's gonna put in these bids where we'll all compete against each other to see who can give Amazon the most money to locate HQ2, and this happens with every major kind of investment. 21:03 And what happened, probably going back 20 years or more, uh, states started creating these, uh, quasi-autonomous non-governmental corporations. The, the, the term quango in the UK they use. 21:16 We don't really use that here, but it's basically a non-profit that's controlled by the state that is where the economic development function is housed. 21:22 And because it's a non-profit, it's exempt from public records laws, and so they don't have to operate with the same levels of disclosure that a government agency would. You can't just FOIA their communications. 21:35 And they, the way the industry works is, you know, you have a site selection consultant. They approach you, and they're asking for information. You might not even know, you know, what client they're representing. 21:47 But at some point, you know, you'll have to sign a non-disclosure agreement, and everybody'll start using a code name. Sorta like a merger and acquisition, everybody starts using a code name to talk about what it is. 21:59 And sometimes, you know, the, the state economic development people even go to local governments, tell them that they need to prove this, that, or the other thing. They might not even know what it is. 22:10 There was a great, uh, article about a metadata center in Louisiana where the governor basically moseyed over to course, you know, key state legislators and said, "I need you to insert this provision into a bill." 22:22 And he didn't know exactly why. It's just like, "Trust me. This is a big economic [laughs] deal for our state. Insert this thing into the bill." And so this is just the way that it works, and then typically 22:33 there's an announcement. S- this auto plant is going to South Carolina or Tennessee, and it's, it's a big deal. Intel is gonna build their chip factory in Columbus, Ohio. 22:45 But how they got to that announcement is typically very opaque. Uh, now there's been a lot of criticisms of this from all sides. Economists basically say these subsidies are, don't work, 22:59 uh, that people are driven by other factors like labor force availability and other, other things. There's some extent to which that's true. 23:09 I do think it's very clear these subsidies do on margin affect where people locate, but this idea is, it's sort of like pro stadium subsidies. Everybody intrinsically thinks they're bad, but we keep doing it anyway. 23:21 And then, you know, there's often political gotchas. Oh, they gave too much money to this company to, to come here. 23:27 And so there has been a lot of dissatisfaction with it, so it, it's not like it was something that everybody was very happy about up until, uh, today. I live in Indiana, also a red state. 23:37 Uh, the, there was a lot of controversies around our economic development organization. The new, the guy who's the governor, he came in. 23:44 One of his campaign promises is, "I'm gonna shut down all these, uh, foundations to take overseas trips, and I'm gonna hire a forensic audit and do all this stuff." So it's, it's just endemic in the system. 23:55 There is a lot of mistrust. But basically, it does all happen behind the scenes, and even the people making the decisions in some cases don't actually know what they're actually making the decision for, right? 24:08 Until kind of it's a done deal. 24:11 Uh, and, and then it's a done deal, and you're kind of expected to kind of vote for some of the approvals that do require a sort of legislative body like a city council or a county commissioners to come in and say approve tax abatements at the local level. 24:26 For state, for state incentives, it's usually at the discretion of these agencies. It's sort of administrative approval. At the local level, there does have to sometimes be elected officials who sign off on this. So 24:40 that, that's where it gets dicey. 24:42 And, you know, the, the attack, the incentives, the abatements at the local county state level, whatever, um, like we cover this industry, and there's a dizzying amount of money flowing in, and, um, that is difficult to grab, and it's a big chunk of money that they're pouring into this, these, these businesses and these developments. 25:03 And you, you, you asked this question, which is, it was... 25:06 You say it's ironic that hyperscalers will pay anything for chips, power generators, but then fight over like tax abatements, which if you consider the whole cost of these projects, they don't seem that big. 25:19 Um, what is going on there? Is this part of like the fumble, like the, the public relations problem that you describe, or is there, or is this just how business has always been done at the, at this scale? 25:32 I think there's a little bit of both. And sorta here's my hypothesis, is bec- because this is how... So think about buying chips. That's a B2B transaction. 25:43 You know, you're gonna call up if you're, you know, the head of Meta, you know, Mark Zuckerberg, who wants some chips, you call up Jensen [chuckles] you guys have talk, you get together at lunch. 25:53 You have a, a different reaction. So you're, you're doing it how it's done in that domain. Then they come into the data center space, and, uh, they're doing it the way everybody... 26:04 "Oh, let's hire the site selection consultants. They're gonna tell us how to go get the tax abatements, and this is just what you do, and this is what everybody does." 26:12 So there is a sense in which they were doing what other people did, but there's also the case that, uh, a lot of times it's not the actual end user who's actually creating the data center. 26:23 You were talking about a company called Iron, uh, while I was in the green room, which sounds to me like a data center company. Yep. That builds data centers which are leased to Microsoft. Yep. 26:33 So ultimately, who is the person doing all this negotiating with the state? It may have nothing to do with the actual end user of that. 26:42 Sometimes it's even a private equity firm or somebody who's basically coming here to run the permitting gauntlet, and then they're gonna flip it to someone else. Or there's many, many, many parties involved. 26:52 It's, it's not as simple as it used to be where, like, it, it's my data center. You know, these, a lot of these people aren't c- you know, keeping it on their books. 27:00 They're partnering with someone else who keeps it on their books, and there's leases. And so there's many parties involved in this, 27:07 and I think some of it, who, who'd made the decision or took the accountability for sort of the PR and local engagement strategy was a big part of it. So there, there is that, but I will say that the industry did go hard 27:22 at state legislators, legislatures as well for statutory tax abatement. So in Indiana, for example, uh, they... And this, I think this was a common one. 27:33 You don't pay any, any sales or use tax on the materials that go into the data center. So they're exempted from that. Uh, they also don't pay any, uh, tax on the electricity that they consume. 27:43 So that's exempted from, from tax. And then there's the option for an, a 50-year tax abatement on personal property. So with something like a data center, there's two kinds of property. 27:53 There's the real property, which is the land and the buildings, and there's the personal property, which is the equipment, which is the chips. Now I will say, I do think 28:02 if you look at the stunning amount of value in the chips and in the electricity that's consumed, if you tax them at the same ordinary rate you say taxed, you know, a machine shop or something, 28:16 it might be way out of line, too high. You know, the tax rates were not put in place for that. So I think having some reasonable lower taxes that treat this like an, an ordinary industrial facility, 28:31 uh, m- might have, might have worked, but they're so abated now that in many places they don't actually pay much in the way of taxes, and I think this was the root of the problem because NIMBYism is endemic everywhere. 28:44 Nobody wants to vote to approve any building anywhere, residential, any kind of building. People come out of the woodwork, at least 25% of the people. They'll, they'll pack the public meeting. 28:54 But if you take something like, say, uh, an automobile assembly plant, that plant is gonna bring 2,000 jobs to your community, and once, let's just say, Honda picks Maryville, Ohio for a plant, 29:10 all of their suppliers have to locate within an hour of them. So you don't have to give as much money away to the suppliers because they have to be there, basically. So the community gets a ton of jobs. 29:22 Whereas with a data center, there aren't very many jobs in a data center. 29:27 Most of the jobs are in the construction, and it's specialized skills in many cases that the local electrician in some small town is not the one wiring up the data center. 29:37 These are big electrical contractors that are assembling this stuff prefabricated, shipping it [chuckles] on site, bolting it, you know. It's a completely different thing than wiring a house. 29:47 And so even a lot of the labor's from out of town. 29:49 And so there's a l- when you're not paying any taxes and you're not bringing very many jobs, there's not nearly as much incentive for these politicians to stand up and say, "Yeah, I'm gonna vote yes anyway because it's going to actually pour money into our budget." 30:05 Now in some places, there's a lot of taxes being paid. Uh, Loudoun County, Virginia is one. There are some other places where there's a lot of taxes coming in. It does vary by place. 30:16 Uh, and I- that's probably one reason why there were no controversies really in Loudoun County until this latest national thing sort of blew up and made everybody not care about it, but it's like, well, of course, they're paying a ton of money in taxes. 30:30 Uh, and most of those are not gigantic ones either. They're more like normal scale databases. 30:34 So I do think the lack of jobs, the lack of taxes, combine it with, again, the cloak-and-dagger NDA-style approaches, all this other stuff, and it's a recipe for people to question the value proposition of it, even when some of the other items like water utilization are really kind of red herrings for the most part. 30:57 Yeah, you do point out, and we talk, we talk about this on the show, like the water for, for... has very unfortunately been a huge red herring because it's not a very good critique of the industry. 31:07 Um, you do bring one which I think is a very nuanced critique, which I wanna get a quick answer for. Um, and that's on the electricity side. 31:17 Um, it seems like the local legislators have kind of caught on to this behind-the-meter trend in Oklahoma and other places. There's the bring your own power initiative. 31:27 Um, but this again is not like a straightforward problem because you, you point out that a lot of this gets into like cost accounting details. Right. Explain this to me. Yeah, so I'm not gonna 31:43 present myself as an expert in electricity accounting 'cause this is not my industry, but I know a little bit about cost accounting, uh, from I did, I did take cost accounting in college. I, I took a lot of accounting. 31:53 And basically, it's just what it says. This is a form of management accounting about how costs are allocated. So think about something like, um, a, a cyber cab ride. What does it cost for, uh, Tesla to deliver a ride? 32:09 Well, there's sort of variable costs, like how much electricity is that is consumed, but most of the costs are like in the car. And so how much of the cost of the car do you allocate to each ride? 32:24 Uh, that's a complicated question. And then of course, upstream of that, what's the cost of a car? How do you allocate the cost of the factory across the cars that it produces? Mm-hmm. 32:34 How do you allocate the cost of the research and development budget? So you could think about something like the electricity utility CEO's salary. Who's paying for his salary? 32:45 Uh, how do we allocate that between different customers? And so it's very easy to say their direct incremental cost associated with the data center will be paid for by that data center. 32:57 You'll pay for the substation that serves you. You'll pay for all these lines. You'll pay for X, Y, or Z. But for all of the sort of general generating and transmission costs, 33:09 the influence on general wholesale markets, it's actually very complicated to think about how you allocate it. So for example, 33:19 uh, my understanding is one of the ways you can allocate [smacks lips] shared costs is by how much energy you use. Everybody plays a pro rata share based on how much energy you use. That seems fair. 33:30 On the other hand, how much infrastructure you need may not be based all on the total energy consumption, but peak energy consumption. So you could also allocate it based on peak consumption. And which method you choose 33:45 has a huge impact on how much each different class of user is supposed to pay. 33:51 And so this is like battle royales going into these rate-making things where all these different groups with their lobbyists are, you know, jockeying for position for what's there. So I think it is very possible 34:05 to have a situation where data centers actually reduce residential, uh, electricity bills because they help cover some of the shared costs 34:16 i- in the system that would otherwise be borne by existing residential and industrial customers. It's also possible that 34:26 residential insur- uh, electricity goes up because they get caught holding the bag on some of these shared costs. And again, it's very, it's very complicated. There's no objective correct answer. 34:40 That's the thing with co- co- cost accounting. There is no objective correct answer. Take a classic one. How do you value your inventory? 34:48 So you buy inventory that comes in the front door, and then you ship it out, you know, or it comes in the back door, you ship it out the front yard. So how do you value it? And how do you do things? 34:57 And so people use methods like first in, first out to like do it, or they do last in, first... There's a mil- there's a million ways, and this is extremely complicated. 35:05 And so I won't say that cost accounting is the equivalent of organic chemistry in that it's like a weed-out course, but it is famously the hardest course as an undergrad accounting, when you start realizing this is a mind-numbingly complex topic. 35:20 So I will say it's not as simple as saying these guys will pay for their own power. 35:24 Now, of course, if they're running all on-site generation, totally detached from the grid, they're building their own kind of microgrid for it, then you could say they're, they're paying for their own, but the minute they're tapping into a broader thing, 35:36 it's actually extremely difficult to disentangle it. 35:39 And so that's why there's these big wars in state like North Carolina, uh, a- and that, and there's different advocacy groups on every side, and, uh, it's a bruising battle. Last question. 35:53 Uh, you touched on this at the top, but I wonder how much of the data center-specific, anti-data center movement that we're seeing is, 36:04 uh, really just the only way people know how to push back against AI or in their fears of AI. Uh, how much of this do you think is actually an, a general AI story versus like, uh, the data center in the backyard story? 36:20 I, I think there's some of it. How much is, is hard to determine. I actually think the tech industry took the wrong lesson from Uber, 36:29 which is with Uber, lesson one, don't even go talk to the taxi and limoni- limousine commission. You ju- You'll never get through that bureauc-- You just go do it. Just go do it establish facts on the ground. 36:43 The second thing is, the second lesson they took from Uber was the, the constituency that will support you in a political battle is your users, right? 36:53 So that's what they did in New York when they wanted to regulate Uber. They created a de Blasio mode, and if you went to de Blasio mode in the app, there were no cars, and, like, people using Uber got very, very upset. 37:03 Well, what happened with AI is everybody uses it and everybody loves it, but AI users are not turning into the political constituency that supports the AI company. 37:13 So I, I'm not getting up and supporting Anthropic because I love Claude the same way that I would've supported Uber, because I think it's the best thing since sliced bread in terms of getting me to the airport or something. 37:26 So I think that the, that sort of model where the users are essentially your, your political constituency failed, and even the people who use AI a lot and love it are very, very skeptical and fearful of it. 37:40 Uh, so I do think there's something there. Aaron Ren, thank you so much for your time today. Love your Substack. Everyone go check it out. Um, Aaron, thanks so much for hanging out with us today. Thanks for having me on. 37:53 See you around. Bye-bye. All right, we have John Todaro of Needham and Co in the wings. We'll bring him on up here to talk a- about data centers and the cost overruns. 38:07 But before that, we have a word from our sponsor, Lagos. [static] If you're using a Bitcoin collateralized lender, you need to ask yourself one question: Do you know where your Bitcoin is? 38:23 If you can't answer that question with confidence, you need to do yourself a favor and check out Lagos Finance. 38:28 Lagos Finance is our preferred Bitcoin-backed lending partner here at Blockspace because they use Bitcoin native smart contracts that ensure you always control the keys to your Bitcoin. That's right. 38:38 With Lagos, you never relinquish self-custody when collateralizing a loan under their services. With Lagos, there's no rehypothecation, no wrapping, no bridging, just competitive rates as low as 8.5 to 10% APR. 38:50 Go to lagos.finance to learn more. Charlie, before... Oh, he's already gone. Oh, I was just gonna say- Back... before we get John up here, I have to say, uh, great segment just then. 39:01 You could've entitled that Kwango's Unchained. Yeah. [laughs] And that's that song and a play about it. [laughs] That's my new favorite term. We're gonna, we gotta incept that, uh, that new term, uh, into the discourse. 39:13 Um- No, 100%. Yeah. All right, get out of here. [laughs] John Todaro, welcome back to Blockspace, sir. How you doing? Doing well. Thanks for having me on again. Yeah, absolutely. 39:26 And at the risk of making two bad puns back to back, I, I could entitle this segment my, uh, um, My Neighbor Todaro. But anyway, we're not here- [laughs] I get it... to talk about Studio Ghibli movies. 39:39 We're here to talk about a great research note that y'all just put out entitled, quote, "It's a Halloween Scare for AI Infrastructure Stocks: Credit, CapEx Overruns, and NIMBYism." 39:51 It takes a pretty good holistic view at a number of the risks, I think, intersecting with all of these stocks right now, specifically CapEx cost overruns, which we're already starting to see in the news a lot more. 40:03 I believe y'all use Cipher as an example here with the fluid stack extension. Yeah. 40:08 Financing snags, and also the fact that deal flow has really slowed down as we are in the shadow of the midterms, and no one wants to ruffle any feathers politically or within their respective communities. 40:22 A good place to start, though, with regards to the Halloween scare tagline. Last week's sell-off was brutal. I mean, just by my accounts, it seems to be the, probably the worst drawdown all year, if not since the summer. 40:36 So as, for a place to start with this interview, [smacks lips] I'm curious your thoughts on that. Is this a sentiment and credit scare only, or are fundamentals actually cracking? 40:47 They're, I would say they're not necessarily cracking yet. But there's fair and real questions around, around that. Are, are we getting close to, to those cracking? Um, so it's not purely sentiment. 41:02 Um, I wish, I wish it kind of were. 41:04 But, but look, i- if you do end up getting CapEx overruns and you can't pass it on to the tenant, you have a lot of these leases that were signed but, but not yet delivered on, that makes the economics less attractive, right? 41:19 And then when you layer in, hey, if, if credit markets and in particular project level debt, if that market is harder to raise financing in, you're likely gonna have to do more dilutive financing, either equity issuance or convertible bond issuance, to kind of, to, to plug the, the CapEx funding gap. 41:40 And if that's the case, I mean, y- you're gonna have some su- surprise dilutive financing that starts popping up, and that's obviously gonna to concern equity investors. 41:49 Um, and then the CapEx overruns eating your economics. So it's, you know, it's, a lot of these guys have reiterated, "Hey, we're on budget, you know, we're okay." 41:59 So from that standpoint, you know, I, I, I don't think the cracks are necessarily there yet. 42:03 But you can see where, you know, we wanna double check, make sure that the cement of the foundation and everything is, is there. Um, because if, if those do happen, then, then that does become an issue. 42:15 The e- economics do get considerably less attractive. Um, and the thing... And, and this is what we kind of had in our note, too. 42:22 The thing that assuages concerns is we get more data points, and the problem with that as you started off, we're not getting data points because d- due to the, the midterm elections and, and some NIMBYism. 42:35 Like, we're, we're kind of on pause for new data centers. So we have to just wait the next at least two weeks to, to get- Any new data point. 42:43 The only data points you could get in the, in the near term, which maybe, um, calm fears is if some of these guys do go out and raise some project-level financing and show, "Hey, look, that market is still pretty good. 42:54 We're getting fairly decent financing rates." 42:57 If that's the case, and there's a number of these that do need to go to market to raise capital, if that's the case, I think that would calm folks down, both on the equity side and the credit side. 43:07 So a lot to unpack with that. I think that was, from what I can see, a good synopsis of the note itself. 43:12 You lead off talking about that the fact that last week's sell-off wasn't just fueled by credit fears, it was specifically those CapEx overruns. So I think that's a good place to start. 43:23 For the companies in your coverage, you modeled $8.37 billion in potential cost overruns. What's the driver here? 43:31 And as a second part to that question, should we start expecting 13 to 15 megawatts, uh, dollars per megawatt just for the powered shell versus 10 to 12 like we've seen? 43:41 Um, so, so first on that, the, the eight billion or so was just, um, a very s- simple example of if we get cost overruns that are looking closer to that, that Cipher number that came out, um, and not even at that level. 43:56 It was, it was merely if we took 20%, if we just took everyone's CapEx for the sites that have yet to be delivered and increased that by 20%, you were talking about an additional eight billion that still needs, that, uh, would need to be funded, and that's on top of the billions that still needs to be raised or that is still earmarked for being raised in the project-level debt market. 44:16 Um, so it's just a, an example of even without extreme cost overruns, we're talking 20%. Understand that's a decent amount. Uh, but you get, you get a, a pretty big number. 44:25 You get eight billion plus that needs to be raised, and that's just for our coverage universe. In the note, that's like, I think that's nine names in the note. 44:32 If you factor in anything CoreWeave needs to do, you know, you're adding on top of that. So anything on the Neocloud side would be separate. This was just the, the, the PSPs, the data center operators themselves. 44:41 Um, so that's that. In terms of your comment on earmarking 13 to 15 million, it's, it's fair. 44:49 Once again, I would say a number of these CEOs have come out and reiterated, "Hey, we're bud- we're, we're on track for our budget." Um, Wolfe CEO, I'm sure you've seen the tweets where, where he put that out. 45:00 Uh, we were at Hutch Riverbend site. I think you guys were there too, by the way. But at the Riverbend site, um, Sean and, and some of the other representatives we spoke with kind of reiterated on budget. 45:12 Um, so i- i- you know, if these, if a lot of these guys are on budget, then you're gonna come in lower than that, than the 13 to 15. But if you wanna be conservative with it, that's probably a fair number to be at. 45:24 I think a lot of the buy side, the institutional buy side accounts we're talking with, um, those guys are starting to underwrite something in the, the, the, the 13 or higher range as a CapEx figure. 45:35 Um, so I, I think it's fair. But, but my comment is if we are talking about 13 to 15 million, then NOI per megawatt does need to go up, or else you're getting yield on c- cost coming down. And, um, you know, and I'm... 45:50 In, in our view, you, you can't, you can't have that compressed too much further. Um, obviously we'd like yield on cost to expand and go the other way, but at, at least kind of be stable. 46:00 Um, so I, I do get concerned if you are expecting 13 to 15 million, y- you kind of need NOI per megawatt to also increase or, you know, you're just getting yield on cost Yeah, and 'cause you're also getting squeezed on the financing side now And then you're getting squeezed on the financing, exactly. 46:14 Yep So just to cap that off, what is leading to these cost overruns, in your view? Is it just redesigns, more expensive equipment? Is it labor shortages and bidding wars for labor and materials? 46:29 Labor has come up a number of times from, uh, our channel check. So I would say labor is a piece. It's a little bit geographic dependent, so, you know, one state location might not be having it as much. 46:40 But labor has kind of consistently gone up, um, and, and it's been, been pointed to. Um, on the material side, some of that as well. 46:47 Um, I, I don't think anyone would say, "Hey, materials, you know, the inflation there is getting better." It is still kind of stepping up. 46:54 Um, but, but labor we seem to hear more of as kind of an unexpected increase to the extent it has. Um, so yeah, I, I would say a few items. 47:03 I don't think there's any one part of the supply chain where it's, it's, you know, you're in a better situation than you were maybe six months ago. 47:11 Um, but labor seems to be the most unexpected increase, at least that's been called out so far. 47:17 So to kind of go to the other side of this, looking at financing, you say in the note, quote, "Our channel checks with data center operators suggest a degree of difficulty in the project-level financing market." 47:29 End quote. What is keeping lenders from leaning in further here? And which sectors specifically between powered shells, hyperscalers and Neoclouds do you think are most exposed or insulated to a tightening credit market? 47:45 I think that PSPs, so your data center operators, are in a little bit better position. If you have an IG offtake, like a Google 15-year contract, I think that is a little bit easier to finance that. 47:59 That market is, y- you know, I would think still open. 48:05 There is just in general a lot of paper tied to AI infrastructure that's out there, and like any market, like the credit guys just need to digest that, um, make sure kind of e- er- everything makes sense and re- go through everything. 48:18 So there is just a lot of paper out there that when we talk to credit guys, there is some just, "Hey, there's just needs to be digestion out there." 48:24 Um, so, uh, you know, uh, we don't wanna give the impression that we think that market's closed by, by any means. That's not really what we're seeing in channel checks. 48:32 But we are from the comp- the, the companies, the, the PSPs that we're talking to, they're saying, "Look, it's, it's getting harder to get done. 48:39 It's, it's, it's a little bit more expensive, and it's harder to just get everyone to the table." 48:43 And part of that is likely because there's a lot of AI infrastructure paper out there that just needs to be digested in total by the credit markets. 48:51 Um, and then but, but, but two, I would say, you know, there's different flavors of it. So if you have an IG offtake, you're gonna be in a better... 48:59 physician than if you, you know, you have like a, a, a Neo Cloud offtake without, without the, uh, the credit quality, um, that's, that's not there. 49:07 And then on the Neo Cloud side itself, it's a little bit different financing. You know, there's more financing tied to the GPUs that are kind of what I would call equipment financing. 49:16 Um, but in general, those guys do need a consistent capital raise from the financing markets, where the data center operators less so. 49:25 Um, so there is kind of a consistent refinancing that the Neo Clouds need to come to market with. And part of it's just 'cause the, you know, their business is, is shorter dated. 49:33 You're doing, in some cases, on-demand, but for the most part, three to five-year contracts. It's different from a PSP that might have a 15, 20-year contract. 49:42 So you go raise one time effectively for that 20-year contract. Maybe you refinance or something in the ABS debt market, but very different from every three years needing this consistent return on the capital markets. 49:55 I don't know if you can speak directly to CoreWeave here, and so if you have to speak in generalities, please feel free to do so. 50:01 But from where I'm standing, there was a lot of chatter last week specifically pointing to those 2030, 2032 bonds unsecured from CoreWeave. There's like four issuances related to its Neo Cloud business. 50:14 And the spreads for that blow- blew out. The yields have come down a little bit, but, you know, it was like 14 to 15% for those last week. Do you think the credit risk there is warranted specifically for CoreWeave? 50:27 And if not CoreWeave, the refinancing risk for these Neo Clouds, considering you do have this mitchmash, mismatch between the credit, uh, the, the credit duration and the duration of the offtake agreements? Um, 50:43 I guess I would refrain from saying whether that's necessarily warranted or not, but what I would say in generalities is there are some risks in the Neo Cloud model, and the PSPs are a little bit more benefit from not sharing some of the same risks. 51:00 Um, I, I... Some of the Neo Clouds... And we, and we had a note out on CoreWeave maybe a week or so prior to this, this Halloween scare note we put out. 51:10 Um, and, you know, we, we do like if you, you own some more of the capacity. If you are more vertically integrated, it, it allows some real estate value to be in the business model, which we do like. 51:22 I think it gives us something we can sort of hang our hand on. CoreWeave has some of their own sites, but a lot of it is third party, um, uh, lease, leased out, right? Um, so that- that's one piece of it. 51:34 Two, there is, in addition to that capital markets risk where you need to keep coming to market to, to refinance, um, there also is tenant resigning risk. 51:43 It's different from the PSP model where you have a 15-year, 20-year agreement with Google. The, on the Neo Cloud side, you have Google, these type of contracts rolling off in three, four years. 51:54 You need to then go out and resign that, and is, is Google and all these operators, were they using you as a stopgap solution, um, or not? 52:01 Are they all gonna to resign at the same level or, or more capacity at that point, right? Where the PSPs, you just don't, you just don't need to do that, right? 'Cause there's the, the 15, 20-year agreement there. 52:13 Um, and then it's, there's obviously just a lot more debt that needs to be layered in for the Neo Cloud model when you, when you're, you're talking about GPU financing and all that. 52:20 Um, what I would say is a positive though is those cloud pricing continues to improve. Um, and you do just see more frequent data points on that, and those kinda consistently improve. 52:35 So to the extent you do have immediately deployable capacity, it, it, it's, it's, it's really good rates right now, right? You're talking 40 million-plus per megawatt. 52:43 Um, and the PSPs, you know, you, you don't quite have that same scenario. 52:47 So in this very attractive environment for compute, for rental costs, like that is a positive for the Neo Clouds the PSPs don't really get to benefit in. 52:57 Um, but, but it, it's still, there's just a, a lot more risk in that model. 53:01 So if we, if you do get concerned about the credit market, there's a lot more credit that, that needs to ultimately go towards the Neo Clouds than the PSPs too. 53:10 So it, it just adds, uh, quite a bit more degree of uncertainty in the Neo Cloud market as PSPs. 53:14 So I wanna pull on that last thread, specifically with the cloud pricing going up and to the right for the Neo Clouds and the hyperscalers. 53:23 At what point do you expect that to flow back down to the PSPs, the power shell providers? 53:29 Specifically considering we just talked about the fact that they're gonna get squeezed from the financing side and potentially from the, from the CapEx side. 53:36 So do you think that there's a high chance that that will eventually flow down to them because they're gonna have to start demanding higher rates for their leases? Y- yeah, to some extent. 53:45 I mean, obviously CoreWeave and these others have their own financing needs though, and, and their, their, their rates are going up as well. So, so that piece is there. 53:53 But I would say it, it would surprise me if, if the clouds were able to keep getting much better pricing, and then it doesn't flow down to higher NOI per megawatt for the, the PSPs. 54:03 So I think the guys who are out there and still negotiating contracts, they're probably making that case right now, and I think it's fair. 54:10 And we, we put it in our note too, like if, if higher CapEx is here to stay, we would think you would negotiate on a yield-on-cost basis. And if your customer is able to get better margin, some of that should flow down. 54:23 And there's, there's other aspects too where maybe you could ease that burden. Um, maybe you split some of the CapEx with the, with the tenant that's signing, right? 54:31 So there's other ways of doing it besides simply NOI per megawatt. Um, but it, it, to us, we do think you're kind of in it now for, for new contracts. 54:40 We would be surprised if you see CapEx materially step up at the same NOI per megawatt that was signed earlier this year. 54:47 Um, and given the cloud model seems to have some flexibility in that in terms of pricing getting better, I would think that would flow down to the PSPs. So- Just... Thank you for that. 54:57 Just two more questions, and we'll get you out of here. You talk in your note that the Companies in your coverage universe have delivered one gigawatt of capacity. 55:06 They've got another 3.8 gigawatts scheduled between Q4 and 2028. Very large window there. What are the biggest threats that you see that could derail this delivery schedule? Um, obviously, yeah. 55:22 I mean, so energization for some of that capacity. 55:26 Like, look, we have at- at least one lease that I can think of off the top of my head where you are still dependent on ERCOT final approvals and that energization schedule as expected, uh, where you do have an underlying lease signed at. 55:40 So some of it is, is energization dependent on ERCOT, and that could, could push you out. Um, but beyond that, I would say a lot of it is design changes and then the CapEx differences. 55:54 And now, typically, the tenant bears that, so you're not gonna see these operators punished for these, these last minute design changes that push out your, your execution phase. 56:05 But if, for your model, if you are doing some present value cash flow analysis and you're expecting, you know, to hit a certain quarter, it does dilute the economics to some extent if, you know, you get pushed out three to six months, right? 56:17 Um, and then if you factor in CapEx overruns. So th- that's what I would say to it. 56:22 Our, our piece on calling that out was just to say, look, a lot of capacity has been signed, and a good chunk of it still needs to be funded and then delivered. 56:32 So if you are seeing financing rates go up and difficulty in that market, it's not like the guys who already signed are, are all good. We already signed the lease. We're good to go. 56:42 Some of that, you know, obviously still needs to be financed and then needs to be executed on. So the point of that was just the gigawatt or so that has been delivered, that's obviously good. Those sites are online. 56:51 You're getting, um, quality economics there. Your CapEx isn't gonna go up. You already delivered the site. But for the other guys, there's still a lot of capacity. 56:58 In fact, the majority of it that y- y- you know, you do still need to deliver and a, and a good perc- percentage of it that still needs to be financed. 57:06 That last point seems to me to be an extremely crucial one, particularly as we go into earnings, which will start hitting the wire the end of this week, next week, and through November. 57:17 Last question for you and just quick thoughts here, John. What are you hoping to see from the names in your coverage that would maybe quell market fears over what we saw last week during the sell-off? 57:31 Yeah, at earnings, what we would love to see is if these guys can y- you know, hopefully someone can get some project level debt financing done, um, by earnings. I think that would be great. 57:41 If, if we saw that one, y- y- you know, you know, maybe that market's not as difficult as some are fearing. And then if the financing rates look fairly attractive, I think that would give us all a lot of comfort. 57:51 Um, for the guys to come out on earnings and to kind of reiterate that they're on budget, um, and maybe point to a few one-offs where we have seen CapEx, uh, go higher. 58:02 If we can truly say, "Hey, look, that looks like a one-off." 58:05 Or if these guys can come out and say, "Hey, you know, there's a, there's a very clear likelihood that we can rework contracts to pass on CapEx to the tenant," um, that would be a positive as well, 'cause that doesn't eat into the economics on yield on cost. 58:19 So there, there's a few different routes it could go, but I think you need the, those three or four data points. And the good thing is this is all stuff that should be discussed at earnings. 58:28 So we should be able to come away with these clear answers. Um, some of it you just might not have done. 58:35 Like if none of these guys get project level debt financing done, you know, the best we can hope for is they give positive commentary on it, uh, which is a little bit of a mixed bag. 58:44 Um, but these questions should all be asked at earnings. So, uh, we'll at least have the, the questions out there and hopefully, you know, management teams answer them in, in, in the way we're looking for. 58:53 Um, but there, there's at least, at least one you can definitively answer. Like if, is your CapEx on budget or not? Right? That is a clear one. 59:02 The project level debt market, there's probably a little bit more wiggle room. You can kind of wiggle out of that answer. But at least one or two of those type of questions we should have clear answers. 59:11 Well, I know, uh, most people listening to this show are eagerly waiting to see what happens. 59:16 I know some are hoping for some deals to be announced, but we'll have to wait and see for a few weeks whether or not earning seasons will bring tricks or treats for your favorite AI stock. 59:25 John, thank you for joining, man. Always a pleasure. Hope you have a great week. Of course. Thank you for having me on. 59:37 Thank you for watching Blockspace Live, co-hosted by Charlie Spears and Colin Harper. We do this every weekday at 1:00 PM Eastern. 59:46 We are Compute's daily live show talking about data centers, interviewing the people building those data centers, and roiling commentary on those data centers. 59:57 If you want more Blockspace content, go to our website blockspace.media. Also, if you made it to the end, thank you. You're a true fan. You are invited to join the Blockspace Insiders group, our X chat. It's free. 1:00:11 Link on the timeline on our X timeline. Go find it, hit us up, and we can chat with you there. Thank you so much for watching. This has been a great Tuesday. We'll see you tomorrow. I'm Charlie. I'm Colin. Adios. 1:00:25 [outro music]