Transcript 0:00 On y'all, welcome back to Blockspace Live presented by CleanSpark. Charlie, 0:04 SB Energy of Stargate fame has s- has filed its S1 to go public via an IPO, and Reuters is reporting that certain bankers that it talked to think that its valuation could clear $50 billion. 0:20 But here's the catch, Charlie, none of their data centers are operational yet. Their only cash flows come from their energy arm. 0:27 We're gonna break down those numbers today after a short stock update at the start of the show. 0:34 Following that, we've got Charlie giving us a breakdown on Vervoe and their recent three-gigawatt framework to build geothermal for data centers for Google. Um, pretty, pretty interesting. 0:47 Not much geothermal activity going on in the United States. Vervoe trying to make it a larger portion of the energy pie. 0:55 And then we will close today's show on a quick note on Bitdeer purchasing 200 acres for its Rockdale facility for $100 million. That's right. Blockspace goes live every weekday at 1:00 p.m. Eastern. 1:10 We are Compute's daily live show featuring quick hits on AI data centers, markets, and emerging technology. 1:18 If you missed the live stream, you can catch the podcast, and newer podcasts are found, RSS, YouTube, Apple, Spotify. And if you, if that's not enough, hit our website, blockspace.media. 1:31 Subscribe to our newsletter, newsletter.blockspace.media. Link to that in the show description. This show is brought to you by CleanSpark, NASDAQ listed and ticker CLSK. More on CleanSpark later on in the show. 1:47 Let's do a quick stock update, Colin. See how our bags are doing. Um, gonna go to Dimetrix obviously for this one, dimetrix.ai. Again, link in video description. Quick little snapshot. 2:02 Let's just take a look at the sector overall. Today, uh, across the data center, uh, stack, everything flat. Year to date, stuff is up big. Memory, storage, custom silicon up 100, 300%. 2:20 In the past month though, we get a little bit of a different look, where, um, the closer you are to actually the, uh, data center side of the business, Neocloud's power shells down two and 11% respectively. 2:35 Let's take a look at power shells. We've been covering this a lot. We've, it's, we're about a couple weeks past, um, an earnings week bonanza from a lot of these companies. 2:44 Year to date, these, uh, the whole sector of power shells are up 30%. But if we're gonna roll the clock back to June, late June, they were up 68, 69%. So on the month, we're actually not too good, down 10, 11%. 3:02 Um, Bitdeer down, Soluna down, Hive, Mara, Anny, Riot, CleanSpark, Core, Cipher, Wolf, Applied Digital, et cetera. 3:13 Um, but we've, they've co- you know, it's, uh, they've, they're kind of like, uh, been struggling since what we call the Leopold liquidation in late July, 3:25 uh, as- They will sing songs of it one day, Charlie They'll sing songs. We already- It will be memorialized by the bards of the market. Exactly. We'll, we'll do podcasts about it. 3:36 Um, so, uh, yeah, power shells, uh, down right now. It, I do think, you know, there, there's a bunch of different factors here. One, the AI trade has cooled off a little bit briefly. 3:49 Two, you have ERCOT batch zero and political risk hitting a lot of these companies. Um, but 3:59 dare I say it, I'm gonna sound like one of these old Bitcoiners who would construct fantastical narratives of why their bag should go up. The fundamentals are good. 4:09 The power pipelines in a lot of these, and the demand for compute is up and to the right. It seems to me to be kind of like an execution risk. 4:19 Um, I'll go to Neocloud's next unless you have a comment on any of these, Colin. Uh, yeah. 4:24 Not, not really much to comment on specific names, but I thought it was interesting yesterday with our, on, during our interview with, um, John from Needham, that he said that he thinks that the political risk is actually weighing on a lot of investor sentiment right now. 4:39 He basically made the case that there are, there's probably a non-inconsequential bucket of investors who just aren't really gonna wanna touch these things through the midterms, or they're not going to put more in. 4:51 If they're not going to taper down their portfolios, they might just keep their hands off for now before they start buying again. 4:58 They wanna see how the midterms are gonna shake out and whether or not the data center pushback will actually materialize into anything more detrimental across the United States for a lot of these companies. 5:08 So I, I don't know. Um, he's, he's, you know, he was working, he works at Needham. He's on the investment banking side. Probably has more of these conversations than we do, um, off the record with some of these folks. 5:20 But it sounds right to me. I don't wanna overstate it though, 'cause I do think that there's a lot of just general turmoil going on right now on the macro. They can't get the 30-year and the 10-year under control. 5:33 Yields keep rising. There, there's been kind of a risk-off appetite, um, or a appe- there's been less appetite for risk, uh, off assets, 5:46 and, uh, you know, we've seen gold and Bitcoin do really well in this environment, which is pretty interesting. 5:52 I also don't wanna overstate the rotation trade too much either, 'cause that might be happening, but who knows if it's enough to actually, you know, bring some of these names down. 6:01 Yeah, the November election should bring a little bit of clarity. Maybe this is a November and December calls on some of these companies while they waffle back and forth for a month or so. I'm gonna keep going. 6:13 Let's look at neo clouds, and the main neo cloud obviously that matters is gonna be CoreWeave. So on the month, neo cloud's basically flat, only down 2%. Year to date, the sector's up 39 to 40%. Um, 6:31 CoreWeave down on the day, 3% for the day. But on year to date, they're actually more down [chuckles] down 9.6%. So that's what's interesting. A lot of these names are actually down year to date. 6:43 Some of them down year over year. But on- most of the names that we cover are down year to date. So if you were bullish, right? You know- Mm-hmm... 6:52 on the one hand, risk-off assets are doing, um, well, except for I guess, I guess technically Treasuries are risk-off, right? Neeva is down 35% on the year, 35% year to date. So wait, I'm sorry, up 20% year to date. 7:09 My bad. [laughs] Okay. Yeah. So, you know, uh, the, the whole market's kind of upside down right now in a lot of regards. 7:17 'Cause like I said, even, I mean, traditionally Treasuries are considered somewhat risk-off, right? And they keep selling off as, as yields keep rising. 7:26 So, um, so the-- but these stocks right now, to your point, Charlie, the fundamentals are pretty strong with regards to pipelines for a lot of these companies. 7:37 If you're bullish on these stocks, you might be welcoming this pullback. 7:41 But I do think we are getting to a point, as we will cover in the next section, that valuations are very rich, and a lot of these valuations are predicated on delivery over multiple years with, with risk that I don't think 7:56 the market is pricing in for everything in a way that would be considered totally responsible. Right? So, you know, uh, that being said, this is a pretty, pretty nasty pullback. Have we seen the end of it? 8:11 A lot of people think that it's going to be-- we're gonna have to see the end of this first CapEx cycle for this actual-- for this bubble to pop, so to speak. 8:19 But again, with SB Energy and with some of these other stocks, the valuations are so sky-high that you do wonder if we're starting to see some trembling in the market. Speaking of SB Energy, I think we cover that next. 8:30 Let's go cover the SB Energy IPO. Colin's dug into it. He's a little skeptical. He'll have-- he'll run you through the math after a word from our sponsor, CleanSpark. [gentle music] We are CleanSpark, 8:44 America's Bitcoin miner. A publicly traded company with the largest operating hash rate, powered entirely by self-operated infrastructure across four states. 8:58 This is our proof of work, and we are setting the standard for what's next. Learn more about the intersection of energy and Bitcoin at cleanspark.com. 9:14 All right, Charlie, potentially one of the most anticipated IPOs of the year outside of SpaceX and Anthropic, if we get it. 9:23 Headline here from Blockspace, S- "SoftBank's SB Energy IPO filing offers eight point eight gigawatts of contracted AI capacity, with most still unbuilt." Most still unbuilt, kind of an understatement here. 9:35 In fact, none of it is built as, as of right now. The lo- most of-- some of it is under construction. 9:41 Its smallest data center, Cosmos, in Travis County, Texas, which is 50 megawatts of critical IT, is under construction. That will actually be leased, or is leased, by SB Energy's parent co, SoftBank. 9:56 But the Stargate project is not projected until 2028. They have another data center in Texas as well that is roughly 750 megawatts of critical IT that is still under construction. 10:10 And Reuters reported here, Charlie, that they believe, or the people that they talk to believe, that its valuation upon IPO-ing could be as rich as $50 billion. 10:22 Now this is for a company that earned $138.7 million during the first half of this year, up 66% year over year. That's from its energy business, a lot of which consists of solar arrays that it has deployed. But 10:41 the reason they're giving it this valuation is that they ha- uh, uh, SB Energy is reporting a $430 billion data center backlog, which is against $438 billion of total backlog for contracts. 10:56 The other eight billion comes from energy. So we said this with SpaceX, and I just wanna get this out of the way right now. 11:05 If I'm commenting on that I think 50 billion is absurd for a company like this, that's solely based on what they currently have operating and what will be near-term operational, not the entire company when these contracts-- or not the company when all of these contracts are satisfied. 11:23 Just like SpaceX, if you're taking SpaceX to be this once-in-a-generation company, you know, this Ad Astra 11:32 company that's going to end up taking humanity to Mars, and they're gonna put data centers in space, and also even if they don't do that, they're gonna be one of the largest AI companies in the world, then $2 trillion doesn't look that crazy on a long enough timeframe. 11:45 50 billion also probably is not that crazy for this company on a long enough timeframe. But based on what they have available right now, 11:53 it to m- I, I think that if you buy this out the gate, you might get a little pop like SpaceX, but you're gonna feel pain later on because I don't think they can sustain 50 billion. 12:02 Reason for that is if you look at that $430 billion backlog, 10% of that Of that contractual value, four- forty-three billion is expected for data centers that are gonna be completed within the next six years, according to Reuters. 12:16 So just ten percent of that four hundred and thirty billion will be unlocked in six years. W- uh, and, and the reason for that is their most-- 12:26 their, uh, their most ambitious project, as we've reported before, Charlie, is part of Project Stargate. It's that ten gigawatt gross, eight gigawatt critical IT s- uh, facility in Ohio, the Port Pike campus. 12:42 That is the campus that SB Energy has a twenty-year lease from with OpenAI. The first phase of that, eight hundred megawatts, is expected in twenty twenty-eight. 12:52 Some interesting details with, with this, Charlie, and this, this S-one for SB Energy has been really good for untangling the web of relationships with regards to NVIDIA, OpenAI, SB Energy, and the US government as well, considering this is part of Stargate. 13:09 So the first a hundred mega- eight hundred megawatts of this Ports Pike campus will be secured from capacity that is existing, mostly existing from AP. 13:18 I think they have a little bit more to make up, um, uh, the gap there between what's existing and what they'll need for the full eight hundred megawatts. The remaining nine point two gigawatts will be nat gas. 13:28 The project is being funded through the US-Japan Strategic Trade and Investment Agreement. SB Energy is acting as the developer and the operator, but the planned owner is actually the United States government. 13:39 And they are building it to be capable of providing excess power into the regional grid for an estimated cost of thirty-three point three billion dollars. So I'm not sure if this is a bull or a bear case. 13:52 I'm gonna go ahead and say it's a bear case, unless, you know, we get some sort of communist government in the next four years. 13:58 Part of the reason why you're probably bullish on SB Energy is the strategic relationship between Japan and the US, and the fact that this is a project that explicitly has backing from the United States government to make sure that it gets off the ground. 14:13 Not-- That's one part of it. Not the least of which also, the two counterparties in this deal are NVIDIA, whose GPUs will be used, and OpenAI, which will use the compute itself. 14:25 Those are-- NVIDIA, the most, the most valuable company in the world. OpenAI, one of the two premier frontier labs. Y- You can't really ask for a better duo unless you have Anthropic thrown in there, right? 14:37 Or maybe SpaceX, if we wanna make that argument. So the counterparties and the parties involved in this are the cream of the crop, and that's going to go a long way for investors wanting a piece of this. 14:47 And then you add the fact that this is one of the United States' premier projects for accelerating AI development. That's kinda the cherry on top. Um, I kinda covered the Milam, Texas site. 14:59 Again, seven hundred and fifty-three critical IT megawatts also going to OpenAI. 15:04 And OpenAI has a vested interest in this, not just from the contractual side of things, but also because they're actually, uh, they're a shareholder in SB Energy. 15:16 In January twenty twenty-six, OpenAI and SoftBank's each, each invested five hundred million in SB Energy for a combined one billion dollar of investment. 15:25 And from that, SB Energy originally issued OpenAI Infrastructure, uh, Holdings a warrant, or, uh, a warrant for eight million five hundred and fifty-four thousand six hundred shares at a one cent exercise price. 15:40 And in the-- And that's when they specifically said the warrant agreement expli- explicitly was a, quote, "material inducement," end quote, for OpenAI to execute its foundation agreement and the Texas leases. 15:52 B- Basically, uh, uh, SB Energy basically saying here they are effectively paying OpenAI, um, to sign these leases, or at least to kinda sweeten the deal for them to sign these leases. 16:03 Now, those warrants were ultimately reduced. 16:06 Um, I'm not really sure why that wa- why that is, but OpenAI now holds three point nine nine one million warrants, which expire January ninth, twenty twenty, uh, twenty thirty-six. And they vest as follows. 16:21 Upon the execution of the leases for Orion and Milam, Milam, [lip smack] 16:32 um, the, uh, eight hundred and sixty-eight thousand, roughly eight hundred and sixty-seven thousand, uh, vest once those leases were executed, so those have vested. 16:41 Financial close on at least seven hundred and fifty-three megawatts, four hundred and nine thousand, uh, of those warrants will vest. 16:50 Um, IPO pricing, once that happens, another eight hundred and sixty-seven thousand, or nine-- uh, eight hundred and sixty-nine thousand will vest. And here's where it gets interesting, Charlie. 16:59 They will-- The-- OpenAI will vest these warrants, 17:03 uh, at a rate of three hundred and sixty-nine thousand shares if the equity value for the company reaches eighty billion, then a hundred billion, then a hundred and twenty-five billion, then a hundred and fifty billion, and then two hundred billion. 17:16 So, I mean, that's an incredibly bullish ramp-up if you're looking at that. And if SB Energy ends up b- you know, hitting two hundred billion or even eighty billion plus, OpenAI will be rewarded handsomely for that. Um, 17:33 here's another interesting twist. SB Energy is also an OpenAI customer. 17:38 It is committed to purchase an aggregate fi- fifty million dollars of OpenAI software and services through twenty twenty-eight, including OpenAI products for its own business. It's not really that surprising. 17:49 You know, if you're going to be hosting them and you're trying to be a company in the twenty-first century in this, the year of AI, then you're gon- you're going to want to have the best of the best in terms of enterprise solutions. 18:01 All right, Charlie, last little bit here, and then I'll wrap up 'cause this is where it gets really interesting with regards to the financial interests of all the parties involved. 18:11 So we've covered this on the show before, but NVIDIA agreed in August to provide residual value guarantees covering approximately 4.25 gigawatts of IT load for the Ohio site with an aggregate maximum liability of $105 billion in the form of a backstop. 18:29 NVIDIA also has the option to support roughly another 3.8 gigawatts, which would essentially cover the remainder of the campus. OpenAI indemnifies NVIDIA for this guarantee, though. 18:43 So this, this backstop from NVIDIA is meant to make sure that SB Energy can complete the project if something goes wrong. 18:52 But if NVIDIA actually has to make payments to SB Energy under the residual value guarantees, OpenAI has agreed to reimburse NVIDIA for those payments. Now, this is between OpenAI and NVIDIA. 19:04 We don't have any other information from the S-1 outside of that, so it's hard to say exactly what that would look like over what timeframe and what the exact terms are. 19:14 But this is about as circular as you can get, Charlie. NVIDIA backstopping SB Energy to guarantee the construction of the site, but if SB Energy doesn't pay them back, then OpenAI is on the hook for that money. 19:30 So it's, it's kind of like, uh, NVIDIA, you know, obviously there's credit risk with OpenAI. They're not even a public company, so they are taking risk with this. 19:40 But if OpenAI pays them back, then can we really call it an NVIDIA backstop? And also the next que- yeah. G- g- go ahead and jump in there if you- Uh, yeah, I mean, I, I hear what you're saying. 19:53 Um, I will say for an energy company to only have two customers, like it... I think that's pretty uncommon. It's not uncommon to have it at the project level. 20:02 You'll often have just one customer for, at the project level. 20:05 But for the entire energy company, a $50 billion enterprise of an energy company that hasn't really broken ground on these significant projects, doesn't even have that much current energy production, uh, very skeptical. 20:20 Now, as you say, you've got some government credibility lent to the situation, but as for the government, it's really more of like a landlord. 20:28 I was trying to like think of analogs or comparisons to the government lending credibility with like close ties and direct financial relationships. 20:38 Two other like, uh, corporate success stories, and the o- only one I could think of was Palantir. Palantir's, uh, 20:48 book and their economics really didn't make sense for a decade or so plus, and now it's very obvious what Palantir, Palantir's value is. The difference is Palantir gets paid by the government. 21:00 In this case, SB Energy pays the government at a, at a simple level. Uh, so it's not... You know, if I, if I... I wouldn't, I wouldn't be touching this IPO. It doesn't make sense to me. 21:17 Uh- No, and you're right about the, the fact that, that, that's something that Reuters and other an- um, well, Reuters is not an analyst, but Reuters reporters and other analysts have brought up is the customer concentration for SB Energy. 21:28 Yeah. 21:29 And I do just wanna return to that point really quickly though, 'cause you do have that customer concentration, but then the company with investment grade credit that is guaranteeing the completion of the site will also be repaid by the offtaker of that compute, OpenAI. 21:45 You know, um, I... It's just, it's just that, that... It- it's such a snake eating its own tail kind of structure, you know what I mean? And 21:56 I, I get that you have to have, for the credit worthiness of the project, having NVIDIA, which is, has some of the highest investment grade credit of any company in the world, obviously their backstop matters a lot. 22:11 So that's-- You ha- you wanna have that in there if you want to be able to finance the construction of the site on reasonable terms if you're SB Energy. 22:19 But I just find it fascinating that OpenAI is ultimately indemnified for that guarantee, so that, uh, like why does it exist at all other than just for the credit relationship? Which is, which is why it does. 22:32 But I do wonder like what happens if SB Energy ends up capitulating, NVIDIA steps in, OpenAI doesn't actually have access to $105 billion to pay NVIDIA for whatever, you know, up to 105 billion to pay NVIDIA for whatever shortfalls the project faces. 22:49 It's just an interesting structure, and I think it will give ammo to a lot of the critics who, who'd point to the circular financing because whereas most of the circular financing that we talk about is, you know, NVIDIA invests in a project that will then buy NVIDIA computers. 23:02 Okay, like you can call that a strategic investment to grow your business, which I actually don't think... That's not uncommon in other industries. 23:09 But this, NVIDIA guaranteeing financial security for a project that will use its computers and then also on the other end saying that the company that ends up using those computers will pay them in case they do have to pay something to step in, to me seems like it could be open to more of a, more of a critique, so. 23:30 And last thing I'll say, NVIDIA's invested, uh, quite a bit, uh, $1.5 billion into, uh, into SB Energy. 23:40 They entered into a $1.5 billion prepaid forward with Energy Global, which is a subsidiary of SB Energy, if I understand the structure correctly. It's kind of complicated. 23:49 But NVIDIA paid the $1.5 billion up front and will receive SB Energy shares following a qualifying financing and listing, um, at basically 90% of the applicable reference price. 23:59 NVIDIA has also agreed to buy another $1.5 billion of Class N non-voting SB Energy shares at the IPO price immediately following the IPO. So- Um, just a web of ownership between SP Energy, OpenAI, and NVIDIA here. 24:16 A lot of interesting details. I recommend going into the S-1, digging around a little bit if you have any other questions regarding it, and I kind of concur with Charlie. 24:23 I would not be buying this, uh, right off the IPO. I, I would wait, just like with SpaceX. 24:28 Yeah, my thought is if you want exposure to energy powering AI data centers, there's probably way better ways with way lower risk. Um, traditional energy companies, for one. 24:42 Uh, perhaps traditional energy companies who have deals with, uh, these AI hyperscalers, such as the next story. 24:51 Which could be richer than not is it's a way to get over-- It's a way to get pre-market exposure to IP, uh, to, uh, OpenAI and before they go public, right? Like they- All right. Yeah, that maybe that's your case. 25:01 It seems to me like [chuckles] if you want pre-market exposure, go buy the token on Hyperliquid. [laughs] It's so much better. [laughs] I... So that's my, that's, that's my not profe- not, uh, financial advice. 25:16 That's your, that's your, uh, newfangled degen zillennial trade. I think it's not even degen anymore. It's- No, it's not... it's ju- it's, it's like capital market strategy now. The- these markets are liquid. 25:28 One, one might even say they're hyperliquid. Okay, enough about that. Um, coming at you from the Wall Street Journal and Blockspace today, um, Fervo, a geothermal energy company, just signed a big deal with Google. 25:44 Uh, specifically 25:48 a geothermal power deal, the largest ever signed by Google, um, for 396 megawatts from Fervo's Cape Station, Utah location, with an option to expand the deal to another megawatt-- or sorry, another gigawatt. 26:09 Fervo recently IPO'd in May, uh, kind of the hot new geothermal company, which I'll, I'll give, I'll give some color to here in a little bit. And this announcement is over, uh, Fervo signing a PPA with Google. 26:26 Uh, Google can add roughly 600 megawatts more by June 2030 for close to a gigawatt total. This is all going to a Google data center. Fervo has some existing contracts with Google and others, Shell, SCE. 26:43 They have a contract pipeline existing of 658 megawatts, so this would be in addition to that, another 400 megawatts, and then possible another 600, so bringing Fervo's total potential contract power pipeline to 27:00 1.658 gigawatts. 27:05 The stock ripped 20% yesterday to $19.75, still down from its IPO price of 70-- of 27, uh, uh, earlier this spring. So there's a couple things. I'll give you the, the caveats first. 27:24 Fervo only has three megawatts of power generation and geothermal, uh, currently active according to their last, uh, filing. That would be, uh, what, what was called, they call it Project Red, and it's in Nevada. 27:38 It's a pilot, came online in '23, and it powers the local grid. They get paid for that. Um, but not a lot. We're talking, you know, in the low six- Three, three megawatts? So just... 27:50 That's the pilot project and- It's the pilot project. Yeah. That's the current known existing operations from what they've publicly said. 27:57 They have another project, um, which should come online in Q4 this year to bring, uh, a full 33 megawatts. 28:06 Um, they have these kind of like pad-based, uh, geothermal systems that they call Geoblocks, which I'll explain in a little bit, that they build in kinda modular fashion. 28:19 And so they're adding another Geoblock to bring the total power generation of their new geothermal technique up to 33 megawatts by year end. Um, in early 2027, they anticipate taking that phase one to 100 megawatts. So 28:34 they have contracts with the big boys, the big names, Shell, Google, et cetera. Now over one and a half gigawatts. Um, and so Fervo basically has to propose projects to Google over the next year or two. 28:49 They pr- have to propose o- I think 400 or 500 megawatts worth of projects in the next year, so Google can decide to act on it. This kinda gives Fervo the golden handcuffs because it, it's almost a de facto exclusivity. 29:03 They say that this basically makes it difficult for them to sign other types of deals with non-Google type customers. Many such cases with companies who have signed with these hyperscalers. 29:15 Um, nevertheless, Google's good for their money. They're one of the best investment grade counterparties and great to have, like, as a flagship tenant. Um, so that's what I have as far as the deal. 29:29 I think what is way more interesting here is just a little, a little explainer of what actually is geothermal and what Fervo is doing and why this is really interesting. 29:41 I can bring a little bit of personal anecdotes in here. Fervo CEO Tim Latimer and I took a bunch of petroleum engineering classes together some 14 years ago at the University of Tulsa. 29:56 Um, I've been on, uh, international trips for extended periods of time with Tim. Uh, so we, you know, we go way back. And so I saw Tim decide to actually go into, uh, oil and gas. Why then go to geothermal? 30:13 Well, because geothermal prior to Fervo and, and similar techniques was kind of geographically constrained. 30:20 You basically have to have a reservoir underneath the earth which already has a certain, like, structure to it where you can inject water, heat that up, and take out the hot air, and use the steam to power turbines to make your e- electricity. 30:39 But... So you can't just do this anywhere. 30:42 However, if you take the two dual revolutionary technologies which unlocked the US shale revolution in the 20- 2000s and 2010s, these two technologies are horizontal drilling and hydraulic fracturing, and you use these sister technologies to, uh, 31:01 basically frack geothermal, uh, reservoirs, you can ma- you can create a, a stimulated area underneath the earth and basically tap into a bunch of potential geothermal activity. 31:18 I have- Basically punching holes in the crust to make sure that you can find the, find the pockets of, uh, steam to power- Yeah... the data centers. Is that basically the idea? Kind of. 31:28 I actually have a, a great, um, explainer from Google on this that I wanna show. Um, sorry for those listening, but this is actually really, really useful to understand. 31:38 Um, they basically drill two well bores alongside each other, uh, horizontally through the, the earth's strata, and they frack one, 31:51 and they pump cold water down that, and it, and the, the cold water then gets heated up and it exits- And then it comes up the other one?... through the other one. It's a really simple concept. 32:03 Uh, and here's a- So these will require, w- these will req- re- require water to be constantly pumped- Yeah... through. Okay. And that's actually, that's, that happens to all geothermal. 32:13 You have to be pumping water constantly in and, and taking it out. Um- Okay, that makes sense. Yeah. So here's, basically Google has, like, a 20-second explainer. It's very, very, um, uh, very, very succinct. 32:24 In northern Nevada, the project started with a well drilled 8,000 feet below the surface, and then extended horizontally. 32:32 To access more heat beneath the ground, Fervo created fractures in the rock and drilled a second horizontal well to intersect them. 32:39 Fervo then pumps cold water underground through the fractures into the second well and up to the surface, harnessing heat from the surrounding rocks along the way. 32:48 The heat is used to generate steam, which produces carbon-free electricity that flows into the local grid. So it's actually a really simple concept. 32:58 So as, and, and this is why it's p- really interesting and promising because if you're a petroleum engineer 33:03 and you don't wanna deal with the volatility of the oil and the gas business drilling activity, um- Come deal with the volatility of the data center industry. [laughs] Yeah, but it's different. Yeah, totally. 33:15 Uh- I'm just, I'm just- It's totally different. And, and it's a lot of, like, analogous skill sets. 33:19 I mean, you need to do h- horizontal drilling, which for those who don't know, you drill down and then you literally are able to turn and curve the well bore and drill another, like, mile or two horizontally through the strata. 33:31 Interesting enough, the specific well types and dimensions and depths that they are doing with the, with the Fervo model are almost a, a perfect copy of the exact type of wells happening in the Permian Basin. 33:44 And so there's a lot of compa- there's a lot of, uh, analogies, uh, and, like, uh, duplicate skill sets here. 33:51 Um, in hydraulic fracturing, you basically shoot these, like, you know, again, like, giant charges down into the well and you, uh, in stages and you create these cracks. 34:03 For oil and gas, you would stimulate those cracks by pumping sand or proppant so that the, the, these, uh, the, the oil can flow from the rock up the pipe. 34:12 In this case, you're actually using that, uh, that to pump water at high pressures down to be kind of this, a, a different type of stimulant to get very hot, and then flow to a nearby adjacent, uh, well bore where it exits. 34:29 Um, so some pretty interesting technology. They're using, uh... They are likely partnered with company Helmerich & Payne, who's a drilling contractor. 34:39 They're one of the premier drilling contractors located in Tulsa, Oklahoma. Uh, and so, uh, pretty interesting. Um- Yeah, that's super fascinating. So I had no idea that they were... 34:53 I mean, I don't know if pioneering's the right word, but that they're probably the f- the foremost, uh, company for using this specific method for producing geothermal. I guess Helmerich & Payne- They are the post... 35:08 I would say, I would say the, the, the poster child company for doing this. Yeah. It- These ideas have been out there. 35:15 Um, it's one of those things that, um, would be like a research paper, and like, um, you know, maybe some, like, demo projects and we can prove that it works. 35:26 But then it takes a company to actually go commercialize it, implement it, and build the system. Yeah. And, and they have, that's what that three megawatt is. They're proving that they can do this, right? Yeah. 35:33 So I, I find this really fascinating. Uh, just a few thoughts. One, just don't tell the environmentalists. Just tell them it's geothermal and don't explain any of the other stuff to them. 35:41 [laughs] Bro, you say, you say frack and people's hairs, hair- Right... is on fire. Right. They'll, they'll freak out. 35:46 And then somehow they'll just think that there's an oil component to this, and then you'll probably have conspiracy theorists writing threads about how the geothermal is just a Trojan horse. 35:55 They're actually pulling oil out of the ground. Yeah. Um, another interesting tidbit, just really quickly, with regards to... So I've always kind of wondered why we don't have more geothermal in the United States. 36:07 It's because you can't just put it anywhere. You have to- Right. Okay. So that's-... you're at the mercy- Yeah... of, like, being in Iceland or certain parts of the Western United States, right? 36:14 So, so it's funny you mention Iceland. So Iceland gets, according to the government, 65% of its primary energy use is geothermal. Um, I think there's- 36:27 That, that energy use encompasses, uh, space heating, 'cause 85% of their space heating comes from it, 30% of the electricity comes from it, but a substantial amount. 36:35 They have 755 megawatts as of 2023, so it's probably maybe a little bit more now. But to say ballpark, somewhere between 750 and me- uh, 750 and 1,000 megawatts of their electricity capacity is geothermal. 36:50 The United States has just over four gigawatts of installed geothermal capacity. For Iceland, their 755 megawatts is 30% of their entire electricity. For us, it's 0.4%. And you don't have as much... 37:05 I mean, Iceland is not an energy rich country. It's a green- No, I know it's not, but I'm just saying just for the scale of it, it's like even something... I mean, four gigawatts is a lot, right? It's a lot. 37:15 My point here is that, like, we don't have very much of it, but f- it's actually quite a lot in the grand scheme of things if we look at one of the countries that's often pointed to as the poster child. Now, I get it. 37:26 Iceland's very small. It has a minuscule population compared to the US, probably on par with, like, what Montana or something like that. Um, 37:35 but I, I was a- I was wondering until you explained it to me just then, I d- didn't really understand why we don't have more of it. 37:42 I also just kind of figured that it was probably just less efficient than something else. I could... I don't know if it's more expensive than- So one thing I'm actually not certain about is how efficient it is. 37:52 Um, you have, like, certain things. Like, you have kind of decline curves, kind of like oil and gas. A well comes online, produces a bunch, declines over time. Similar with these, uh, geothermal formations. 38:03 Um, I haven't, like, looked at the research, nor am I really qualified to make an assessment on this. Do you wanna build a data center 38:11 that's gonna consume half a gigawatt based upon decline curve assumptions of, like, a rock that you haven't tapped before? 'Cause I, 'cause that's... Uh, I'd be risk- I'd be careful there. 38:23 There's also, um, uh, the cost. So, um, Fervo's geothermal model, uh, at their Cape Station Phase 1, they are building out to be around seven thou- it's gonna cost about $7,000 per kilowatt to produce. 38:41 Phase 2 drops it at 5.5 thousand per kilowatt, and then targeting 3,000 per kilowatt over time- So seven million per megawatt? Is that all in? Like, that's- So this is to produce the energy though. 38:52 This is not, like, a- Oh, that's not even to do the... But, but that's what I mean. Is that to... Is that just once the fracking has, has been done and everything's in place? This is once the site... 39:01 This is basically all in, like, site is online and producing, uh, kilowatt hours, and that's gonna... So that's, you know, basically how much it costs. Um, 39:10 but we don't ha- like, 'cause we cover data centers, we know, like, what a cost per megawatt is and, you know, maybe how much GPUs would cost, but not the energy production. 39:19 When you look at how much it costs to build one of these geothermal type systems at 7,000 per meg- per kilowatt, let's just even say they hit their 5.5 and 3,000 per kilowatt hour, um, per kilowatt over time. 39:35 A combined cycle natural gas plant costs about, um, $800 to $1,000 per kilowatt. Solar, uh, is about 1,500. 39:49 Solar plus four-hour storage, 2.6 thousand. Wind, 1,500. Conventional geothermal is $3,900, maybe $4,000 per kilowatt. 40:02 So, um, this is actually more in line with what it costs for a small modular reactor, around the 8,900 to $9,000 per kilowatt to, uh, build these things. So it's very, it's very expensive. 40:16 Even when you assume they're gonna hit their cost, their end game cost of $3,000 per kilowatt, it's still puts you at, like, the upper end of the curve of different energy types. 40:26 The thing is, is that, um, you have highly transferable skills in service companies who can do these from oil and gas. H&P already has rigs in Utah. 40:36 Um, we, I have access to an internal data set from a different activity that I do, and they have rigs in Utah currently that are perfectly suited for drilling these long, deep, permeastyle laterals. Um, and, 40:50 uh, there's a lot of environmental regulations, and you can't just drill oil and gas everywhere. While there is oil and gas, it's not as developed in Utah or Nevada. Uh, geothermal can be great. 41:01 You can get credits for it. If you're Google and have committed to powering your data centers with X percent, 80 to 100% renewable energy over the next two or three decades, then, 41:12 uh, you do have to diversify your energy, uh, sources, and this is a great example of that. 41:19 Um, and, uh, even though it's not, like, as cost efficient, I'm kind of a believer in, you know, developing new energy tech across the board. That's a great thing. It's great for industrialization. 41:32 Might not be the best dollar spent today, but long term, uh, it's a great, like, technical revolution, so. $7,000 per kilowatt is kinda crazy, and I wonder how much it actually costs to, to get to that point. 41:50 Like, I would like to know what the CapEx costs for actually pr- for building the data center- Well, there's a lot... Yeah, well, I think- For constructing the power plant and then fracking- Yeah... 41:58 to get it off the ground. Like, what would that be? Yeah. Well, my boy Tim is at the company helm, and I liked Tim. Had a number of beers with him back in the day. Good old boy. 42:08 Great to see him running a public company with Bill Gates, uh, backing it, and Google as a gigawatt plus counterparty. Shout out to Tim Latimer. We're gonna keep on going. We're gonna talk about Bitdeer. 42:22 It's dropping 100 million on 200 acres after a word from our sponsor, Lygos. 42:33 If you look into the annals of Bitcoin, you'll find multiple examples of Bitcoin-backed lenders playing funny games with clients' coins and losing them. 42:42 We've seen Celsius, we've seen BlockFi, and we do not want you to be the next victim of such funny business if you're using a Bitcoin-backed lending company. So do yourself a favor. 42:54 If you want to lend your Bitcoin, check out Lagos Finance. They are our preferred Bitcoin-backed lender here at Blockspace, and they make sure that you always control the keys to your Bitcoin. That's right. 43:07 With Lagos, they use Bitcoin-native smart contracts so that you always self-custody your coins when you are taking out a loan that is collateralized by Bitcoin through their platform. 43:18 With Lagos, there's no rehypothecation, no wrapping, no bridging, no funny business, just competitive rates as low as 8.5% to 10% APR. Go to lagos.finance to learn more. All right, Charlie, one last story. 43:33 Not too much to note on this one, more of just a shout-out. Bitdeer has s- has executed a $100 million payment for 200 acres near its Rockdale data center. This is coming at y'all from Blockspace. 43:49 Bitdeer completed a roughly $100 million cash purchase of 200 acres near Rockdale, Texas, on Tuesday, securing fee simple land for a planned AI and HPC expansion. 43:59 Bitdeer said its Milam County site- sites have 563 megawatts of interconnected capacity and a dedicated water supply. Existing plans would increase capacity to f- 742 megawatts in the county. 44:13 The operator controls about 255 acres and 242 megawatts across existing and planned power capacity. 44:19 Now, there are still some questions with regards to just exactly what has been secured, as our friend, as friend of the show, Steven Glagola, said in his recent research note with KBW. 44:35 Glagola noted in the note that the purchase removes a primary development constraint at Rockdale, but said it remained unclear whether the relevant power interconnection and water rights transferred with the parcel. 44:47 Glagola said the transaction leaves several material infrastructure questions unresolved. 44:50 The firm could not determine whether interconnection and water rights controlled by SLR, which KBW understood to be the seller, transferred to the land or w- or were covered by a separate agreement. 45:02 Ownership of SLR's Rockdale substation also remains unclear. During a May site visit, KBW found that Bitdeer did not appear interested in buying the aging substation and had not procured a replacement. 45:16 Tuesday's announcement provided no update on that process. So it seems like Bitdeer doing 45:23 a decent job making sure that they can secure what they need to for a potential AI site here at Rockdale, but still some questions regarding water rights and additional power rights, um, as well as the actual infrastructure on the site itself. 45:38 Bitdeer did not fully disclose all of these, a- a- all of these considerations for the site itself. And I do want to just reiterate, Bitdeer currently does not have, um, does not have a lease at this site. 45:55 Uh, they are shopping it, no doubt. We know that Riot has signed leases for Rockdale, one with AMD and another with a leading frontier lab. 46:04 So it's possible that we will see it, uh, sometime soon, but so far they have not inked anything as it stands. Well, land, dare I say, is probably the easier part. 46:21 I know that they say they ain't making any more of it, but right now the land is not typically the scarce. It's the, you know what they say about substations and power pipelines, [chuckles] 46:34 they ain't making too much more of it. So, uh, we'll see. Bitdeer, uh, cr- a wild story following that company. Um, looks like they wanna expand their... I- is their, is this their crown jewel site, the Rockdale site? 46:50 Um- This is like the, this is like their prominent one when they first came to the US just across the street from Riot for a little while. Yeah. It's, it's their biggest, I believe. Um, they have a number of larger... 47:03 Like, they have a few sites in Ohio. Yeah, the Bhutan deal. Yeah. Yeah. I mean, they have sites really all over the world, and then they have that one in Ohio that's currently- Yeah... 47:13 in litigation that, that they were ar- that they were kind of d- speaking of, um, banner sites for them, that one in Ohio that they wanted to convert for AIHBC, I think like 500 megawatts was the target, is currently in litigation over a dispute because they have a shared tenant on their lease there. 47:31 So, but yeah, I mean, to your point, probably one of the more attractive sites. Um, Rockdale is pretty close to Austin and San Antonio. It's also, I mean, not super close to Houston, but it's, it's around, right? 47:47 So I wouldn't be surprised if we see them ink a lease for this over, you know, maybe before the year's out or early next year. Yeah. Also, this in from Blockspace right, uh, before we went live. 47:58 Investment bank Keefe, Bruyette & Woods' coverage on Bitdeer following the Rockdale land acquisition, issuing a price target for $10. 48:06 Quote, "The Rockdale land acquisition is a positive step for unlocking AIHBC opportunities. 100 million purchase price came in below our prior expectation. 48:15 However, it remains unclear to us whether SLR-controlled interconnection water rights were transferred in the transaction." So pretty much what you already said, but stands to be iterated, $10. 48:28 They're waiting to put a $10 price on it, is that what that was? Yep. That's what it said. It's at $10.46 right now, so- Congratulations. Mission accomplished. Congratulations. 48:39 We're gonna-- I mean, technically, actually, let me pull up what it currently is right this moment. Um, yeah, $10. 10.50. [laughs] So, you know, maybe they issued that, uh, because it was 8.70. 48:53 Well, and also Steven, I s- There we go... Steven's, well, he's pretty conservative on a lot of his calls, right? So, like, he's actually one of the more moderate investment bank analysts. 49:04 Like, he doesn't come out with these, like, really just absurd and, um, kind of high-flying valuations for these companies, so. Yep. All right. Thanks for hanging out with us today on the live stream. 49:21 If you want to meet us in person, we'll be at Yotta 2026 at the end of this month in Las Vegas. Blockspace is proud to partner with Yotta 2026. 49:30 Join 6,000 industry leaders in Las Vegas, September 28th through 20- sorry, September 28th through 30th for three days of insights, networking, and partnerships, driving the next era of AI infrastructure. 49:43 Use code Blockspace20, that's Blockspace, number 20, one word, to save 20% on your pass. Check out the full a- agenda and register at yotta-event.com. Thank you for watching today's live stream. 49:57 We do this every single weekday at 1:00 PM Eastern. We are Compute's daily live show. Check out our newsletter, dropped in your inbox every single day, newsletter.blockspace.media. Link in the show description. 50:12 Our sponsor is CleanSpark, NASDAQ-listed ticker CLSK. See you tomorrow. I'm Charlie. I'm Colin. Peace. [outro music]