
The data center political war claimed another casualty yesterday at the stroke of Pennsylvania Governor Josh Shapiro’s pen.
The potential 2028 presidential candidate signed Executive Order 2026-05 under the title “Protecting Pennsylvania Consumers from Data Center Impacts.”
Unlike New York Governor Kathy Hochul’s July executive order, which yokes data center developers under at least a one year moratorium, Shapiro’s action is not an outright ban. But this distinction belies the fact that Executive Order 2026-05 mandates onerous requirements for developers and extremely punitive measures for non-complying companies.
It’s about as stringent an action a government can take against the industry without outright banning data centers.
Per the order, Pennsylvania’s GRID guidance — a framework Shapiro rolled out in February — is now basically a requisite (not a suggestion) for permitting approval. Now, the PA Department of Environmental Protections (DEP) will evaluate projects only if they sign a GRID commitment. Additionally, data center projects must secure all local zoning and permitting approvals before they can receive state-level approval.
The most consequential elements of this GRID framework are as follows:
Data center developers must secure enough incremental capacity to cover 100% of peak demand and enough incremental energy to cover 100% of annual electricity consumption. In practice, that means a covered data center cannot simply rely on PA’s existing generation — it must be matched with new or expanded generation added since January 1, 2025 that qualifies as incremental. That supply can be on-site or procured from qualifying off-site resources, subject to PJM deliverability requirements.
Operators now have hard clean energy requirements (nuclear, hydro, wind, solar, fuel cells, geothermal, clean-hydrogen resources, or battery storage). Their total energy draw must comprise 10% clean energy by 2027, 14.5% by 2030, and 32% by 2035. Companies can pay a yet-to-be-determined fine to duck this requirement.
Data centers are required to create at least 200 construction jobs at prevailing rates during construction. They also must create 50 full-time jobs paying at least 125% of Pennsylvania’s statewide average wage within four years of the site’s commencement and ensure this payroll equals at least $1.5 million in annual gross compensation after this date. Plus, they have to commit at least $250 million in cumulative new investment into the site, with no specific timeframe given for this provision.
Shapiro is also pressing his energy council to steer PA Public Utilities Commission rules to require data centers to bankroll new transmission and other grid costs, in addition to stripping data centers of their critical load status (meaning they must curtail before other rate payers in the event of an energy shortfall). The executive order does not set these rules, but it encourages the PUC to consider them (similar to the new regulations we’re seeing in Texas with ERCOT/PUC’s revamp).
The executive order also erects new reporting requirements and red tap hurdles
New requirements for annual disclosures, beginning July 1, 2027, on monthly electricity and natural-gas consumption, peak energy usage, water consumption and source, and projected energy/water demand.
A community-benefit agreement with municipal governments addressing project phasing, noise/vibration/light mitigation, traffic, air quality, aesthetics, emergency services, local financial contributions, and other issues (this includes three public meetings on this info.
Environmental requirements, including performance-based facility certifications demonstrating energy/water efficiency, use of zero-emission backup systems where applicable or generators meeting Tier 4-equivalent emissions standards, limit generator operations, and installation of at least three continuous air-quality monitors (with this data made publicly available).
GRID’s Consent Order and Agreement is legally binding and requires applicable obligations to flow through to the data center’s operator, tenants, and other controlling end users. Developers must also disclose the identity of those parties to the Pennsylvania DEP within five business days of entering into a commercial agreement.
There are a few other odds-and-ends, but those are the most pressing changes.
Data center stocks with portfolio concentration in-state sold off on the news. Nebius (NASDAQ: NBIS) closed down 9.9%, while Keel Infrastructure (NASDAQ: KEEL) and Amazon (NASDAQ: AMZN) originally dipped on the news before closing up 2.9% and 2.5%, respectively.
Keel’s Sharon and Panther Creek sites should be grandfathered in, having secured zoning and most of the relevant permitting locally before the Executive Order’s August 18, 2026 cutoff, with the remaining permitting applications submitted but pending approval. Scrubgrass is another case entirely, however, as that site is still in the power study phase. Keel’s zoned sites arguably just became more valuable, so that’s a merit in their favor.
That said, the jobs mandate, incremental energy provision, and clean energy requirement are new hurdles that Keel and others will have to clear. The employment provision is probably easy enough to satisfy, but the other two could pose legitimate challenges.
Not that Keel is a special case here. Every operator in the state will now have more work ahead of them to realize their plans, and the looming question now is whether Shapiro just torched PA’s potential to be a rust-belt data center powerhouse.
-CMH
Daily Podcast

BLOCKSPACE
Josh Shapiro’s Data Center Executive Order (and What it Means for KEEL, NBIS), Plus a Look at National Data Center Pushback
In The News
Bitdeer contracts half of 9.5 MW Malaysia AI facility under $400 million deal
Bitdeer contracted approximately half of its 9.5 MW A102 facility in Malaysia before energization under a five-year offtake commitment carrying about $400 million of expected revenue.
Services are scheduled to begin in the first quarter of 2027. The liquid-cooled, multi-tenant facility is designed for NVIDIA GB300 NVL72 deployments and represents part of Bitdeer AI’s target of delivering up to 350 MW of data center capacity by the first quarter of 2028.
Bitdeer reported an active AI cloud pipeline exceeding $2 billion across roughly 24.5 MW. The company generally structures AI cloud contracts with customer prepayments covering more than half of the related capital expenditure.
Republican Senate arm warns AI companies over data center anger: Axios
The Senate Republican campaign arm privately warned AI companies that public anger over data centers threatens the party’s chances of retaining a key Ohio Senate seat.
Axios reports that internal polling places data centers among the country’s least popular infrastructure projects. Democrat Sherrod Brown has used the issue against Republican Jon Husted, while a recent Fox News poll showed Brown ahead by eight points.
The memo urges AI companies to explain who benefits from their projects, who bears the costs and why host communities should support them. Republicans fear that a loss in Ohio could slow AI infrastructure development across the country.
CFTC requests public comment on compute derivatives
The CFTC is studying how derivatives markets could develop around compute capacity as AI infrastructure becomes a larger commodity market.
The agency is seeking feedback on compute spot-market liquidity, manipulation risks, customer protections and perpetual compute futures. Comments will remain open for 60 days after the request appears in the Federal Register.
Chairman Michael Selig described derivatives as a necessary piece of a mature U.S. compute market. The request marks an early federal step toward rules for trading financial products tied to compute.
Nebius proposes $4.5 billion convertible notes to fund AI cloud expansion
Nebius proposed a $4.5 billion private offering of senior unsecured convertible notes, split between $2.75 billion due in 2030 and $1.75 billion due in 2034.
Initial purchasers could buy another $675 million, bringing the potential raise to $5.175 billion. Nebius plans to spend the proceeds on data centers, new sites, GPUs and its full-stack AI cloud.
The financing follows roughly $5.7 billion of Q2 spending. Nebius still expects $20 billion to $25 billion of capex this year and 800 MW to 1 GW of connected power by year-end.
Greenup County exempts TeraWulf campus from six-month data center pause
Greenup County approved a six-month moratorium on data center operations while exempting TeraWulf’s planned Muskie Data Campus.
TeraWulf owns or controls roughly 285 acres at the EastPark Industrial Park. The company expects the site to accommodate more than 1 GW, with the first 500 MW beginning to ramp in the second half of 2028 and another 500 MW targeted for 2030.
The pause gives local officials time to develop rules covering noise, lighting, power demand and other community impacts. TeraWulf CEO Paul Prager has said Muskie could eventually expand to 2 GW.
Post of the day
Before you go, do you mind filling out this quick survey?
It truly helps us understand who is reading plus listening to Blockspace!

